Preshift examination at fixed intervals.
30 CFR 75.360(g) · $151.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $1,219.00 proposed penalty
Accumulation of combustible materials.
30 CFR 75.400 · $165.00 proposed penalty
Electric equipment; examination, testing and maintenance.
30 CFR 75.512 · $165.00 proposed penalty
Air quality.
30 CFR 75.321(a)(1) · $165.00 proposed penalty
Ventilation controls.
30 CFR 75.333(h) · $165.00 proposed penalty
Roof bolting.
30 CFR 75.204(f)(7) · $165.00 proposed penalty
Electric equipment; examination, testing and maintenance.
30 CFR 75.512 · $165.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · $165.00 proposed penalty
Accumulation of combustible materials.
30 CFR 75.400 · $165.00 proposed penalty
Installation of high-voltage transmission cables.
30 CFR 75.807 · $165.00 proposed penalty
Regular Safety and Health Inspection
162.8 on-site hours reported
Mine ventilation plan; submission and approval.
30 CFR 75.370(d) · $366.00 proposed penalty
Storage of liquefied and nonliquefied compressed gas cylinders; requirements.
30 CFR 75.1106-3(a)(2) · $165.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · $165.00 proposed penalty
Roof bolting.
30 CFR 75.204(f)(4) · $165.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · $592.00 proposed penalty
Methane monitors.
30 CFR 75.342(a)(4) · $165.00 proposed penalty
Condition and examination of firefighting equipment.
30 CFR 75.1100-3 · $151.00 proposed penalty
Automatic fire sensors and manual actuators; installation; minimum requirements.
30 CFR 75.1107-4(c) · $165.00 proposed penalty
Automatic fire warning devices; actions and response.
30 CFR 75.1103-5(d) · $165.00 proposed penalty
Automatic fire sensor and warning device systems; examination and test requirements.
30 CFR 75.1103-8(c) · $151.00 proposed penalty
Fall of roof or back
Accident only
Accident narrative
An unplanned roof fall occurred on 4/16/2025 at approximately 10:30 am on the 1 section, which is currently retreat mining in front of an MRS in the No. 3 Entry at 16 crosscut on the 2 left panel. The fall was approximately 8' x 8' x 3' thick.
Non-Injury Accident Investigation
4.0 on-site hours reported
Violation — cited standard not reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.