Electric wiring and equipment; installation and maintenance.
30 CFR 77.516 · $151.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
30 CFR 77.1606(c) · $151.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
30 CFR 77.1606(c) · $151.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
30 CFR 77.1606(c) · $151.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
30 CFR 77.1606(c) · $151.00 proposed penalty
Drilling; general.
30 CFR 77.1007(a) · $151.00 proposed penalty
Machinery and equipment; operation and maintenance.
30 CFR 77.404(a) · $883.00 proposed penalty
Examination and maintenance of firefighting equipment.
30 CFR 77.1110 · $151.00 proposed penalty
Powered haulage
Days away from work only
Accident narrative
Employee was operating a rock truck on 09/05/2025 and felt pain in lower back after hitting a pothole. EE went to the Emergency Room on 10/05/2025 and the CT Scan showed bulging disc. EE had a follow-up appointment on 10/13/2025 and they want Pre-Approval for PT and MRI. Employee began missing work on 10/08/2025 and estimated return to work is 11/24/2025.
Health Technical Investigation
4.5 on-site hours reported
Verbal Hazard Complaint Inspections
2.0 on-site hours reported
Loading and haulage equipment; operation.
30 CFR 77.1607(i) · $398.00 proposed penalty
Machinery and equipment; operation and maintenance.
30 CFR 77.404(a) · $592.00 proposed penalty
Loading and haulage; general.
30 CFR 77.1600(b) · $151.00 proposed penalty
Accumulations of combustible materials.
30 CFR 77.1104 · $592.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
30 CFR 77.1606(c) · $398.00 proposed penalty
Hazard training.
30 CFR 48.31(d) · $398.00 proposed penalty
Highwalls, pits and spoil banks; plans.
30 CFR 77.1000 · $267.00 proposed penalty
Machinery and equipment; operation and maintenance.
30 CFR 77.404(a) · Significant and substantial (S&S) · $245.00 proposed penalty
Stripping; loose material.
30 CFR 77.1001 · Significant and substantial (S&S) · $398.00 proposed penalty
Highwalls, pits and spoil banks; plans.
30 CFR 77.1000 · $267.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
30 CFR 77.1606(c) · $151.00 proposed penalty
Loading and haulage equipment; operation.
30 CFR 77.1607(i) · Significant and substantial (S&S) · $1,320.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
30 CFR 77.1606(c) · $151.00 proposed penalty
Loading and haulage equipment; installations.
30 CFR 77.1605(a) · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.