Turquoise Ridge safety activity
MSHA violations, accident reports and inspections.
Safety activity
Testing grounding systems.
30 CFR 57.12028 · $1,550.00 proposed penalty
Testing grounding systems.
30 CFR 57.12028 · $697.00 proposed penalty
Temporary, portable containers.
30 CFR 47.44(b) · $398.00 proposed penalty
Safe access.
30 CFR 57.11001 · $818.00 proposed penalty
Ground support use.
30 CFR 57.3360 · $1,550.00 proposed penalty
Ground support use.
30 CFR 57.3360 · $1,550.00 proposed penalty
Spillage and leakage.
30 CFR 57.4102 · $1,968.00 proposed penalty
Inspection and cover plates.
30 CFR 57.12032 · $883.00 proposed penalty
Handrails and toeboards.
30 CFR 57.11002 · $959.00 proposed penalty
Housekeeping.
30 CFR 57.20003(c) · $883.00 proposed penalty
Roadway maintenance.
30 CFR 57.9313 · $1,818.00 proposed penalty
Operators' stations.
30 CFR 57.14103(b) · $1,126.00 proposed penalty
Spillage and leakage.
30 CFR 57.4102 · $5,574.00 proposed penalty
Ground support use.
30 CFR 57.3360 · $1,679.00 proposed penalty
Roadway maintenance.
30 CFR 57.9313 · $1,818.00 proposed penalty
Roadway maintenance.
30 CFR 57.9313 · $1,126.00 proposed penalty
Ground support use.
30 CFR 57.3360 · $1,679.00 proposed penalty
Spillage and leakage.
30 CFR 57.4102 · $1,968.00 proposed penalty
Testing grounding systems.
30 CFR 57.12028 · $1,550.00 proposed penalty
Spillage and leakage.
30 CFR 57.4102 · $1,968.00 proposed penalty
Housekeeping.
30 CFR 57.20003(a) · $2,503.00 proposed penalty
Regular Safety and Health Inspection
123.0 on-site hours reported
Inspection.
30 CFR 57.4201(a)(1) · Significant and substantial (S&S) · $6,540.00 proposed penalty
Testing grounding systems.
30 CFR 57.12028 · $2,712.00 proposed penalty
Guarding electrical connections and resistor grids.
30 CFR 57.12023 · $398.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.