← Trace Fork #2

Trace Fork #2 safety activity

MSHA violations, accident reports and inspections.

2025-01-01 – 2026-10-28Database snapshot · 2026-10-28

Safety activity

  1. Spot Inspection

    inspectionRecord F02B8B0

    2.5 on-site hours reported

  2. Mine ventilation plan; submission and approval.

    violationRecord 5085516

    30 CFR 75.370(a)(1) · $151.00 proposed penalty

  3. Regular Safety and Health Inspection

    inspectionRecord F014A14

    31.0 on-site hours reported

  4. Spot Inspection

    inspectionRecord F00510C

    8.5 on-site hours reported

  5. Spot Inspection

    inspectionRecord F014A10

    2.0 on-site hours reported

  6. Spot Inspection

    inspectionRecord F014A0B

    2.0 on-site hours reported

  7. Changes; notification by operator.

    violationRecord 5082743

    30 CFR 41.12 · $151.00 proposed penalty

  8. Regular Safety and Health Inspection

    inspectionRecord F0326AF

    23.5 on-site hours reported

  9. Cable fittings; suitability.

    violationRecord 5085453

    30 CFR 77.505 · $151.00 proposed penalty

  10. Regular Safety and Health Inspection

    inspectionRecord F003CE7

    24.0 on-site hours reported

  11. Violation — cited standard not reported

    violationRecord 5085450
  12. Highwalls, pits and spoil banks; plans.

    violationRecord 5085449

    30 CFR 77.1000

  13. Violation — cited standard not reported

    violationRecord 5085448
  14. Mine emergency evacuation and firefighting program of instruction.

    violationRecord 5085447

    30 CFR 75.1502(a)

  15. Mine ventilation map.

    violationRecord 5085446

    30 CFR 75.372(a)(1)

  16. Mine ventilation plan; submission and approval.

    violationRecord 5085445

    30 CFR 75.370(a)(1)

  17. Roof control plan.

    violationRecord 5085444

    30 CFR 75.220(a)(1)

  18. Weekly examination.

    violationRecord 5085443

    30 CFR 75.364(a)(1)

  19. Violation — cited standard not reported

    violationRecord 5085442

    $168.00 proposed penalty

  20. Highwalls, pits and spoil banks; plans.

    violationRecord 5085441

    30 CFR 77.1000 · $168.00 proposed penalty

  21. Violation — cited standard not reported

    violationRecord 5085440

    $168.00 proposed penalty

  22. Mine emergency evacuation and firefighting program of instruction.

    violationRecord 5085439

    30 CFR 75.1502(a) · $168.00 proposed penalty

  23. Mine ventilation map.

    violationRecord 5085438

    30 CFR 75.372(a)(1) · $168.00 proposed penalty

  24. Mine ventilation plan; submission and approval.

    violationRecord 5085437

    30 CFR 75.370(a)(1) · $168.00 proposed penalty

  25. Roof control plan.

    violationRecord 5085436

    30 CFR 75.220(a)(1) · $168.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.