  1. Inspection and cover plates.

    violationRecord 5054636

    30 CFR 57.12032 · $1,219.00 proposed penalty

  2. General requirements.

    violationRecord 5054489

    30 CFR 57.4200(b)(2) · $697.00 proposed penalty

  3. Inspection and cover plates.

    violationRecord 9340079

    30 CFR 57.12032 · $1,320.00 proposed penalty

  4. Safe access.

    violationRecord 9340078

    30 CFR 57.11001 · $432.00 proposed penalty

  5. Inspection and cover plates.

    violationRecord 9340077

    30 CFR 57.12032 · $1,320.00 proposed penalty

  6. Testing grounding systems.

    violationRecord 5054635

    30 CFR 57.12028 · $504.00 proposed penalty

  7. Insulation and fittings for power wires and cables.

    violationRecord 5054634

    30 CFR 57.12008 · $697.00 proposed penalty

  8. Construction and maintenance of ventilation doors.

    violationRecord 5054487

    30 CFR 57.8531(e) · $177.00 proposed penalty

  9. Barricades and warning signs.

    violationRecord 5054486

    30 CFR 57.20011 · $288.00 proposed penalty

  10. Correction of hazardous conditions.

    violationRecord 9340076

    30 CFR 57.3200 · $267.00 proposed penalty

  11. Storage of flammable liquids underground.

    violationRecord 9340075

    30 CFR 57.4460(a)(1) · $697.00 proposed penalty

  12. Securing movable parts.

    violationRecord 9340074

    30 CFR 57.14206(b) · $697.00 proposed penalty

  13. Securing movable parts.

    violationRecord 9340073

    30 CFR 57.14206(b) · $697.00 proposed penalty

  14. Correction of hazardous conditions.

    violationRecord 9340072

    30 CFR 57.3200 · $883.00 proposed penalty

  15. Communication with refuge chambers.

    violationRecord 5056008

    30 CFR 57.11054 · $267.00 proposed penalty

  16. Protection of gas cylinder valves.

    violationRecord 5054633

    30 CFR 57.16006 · $313.00 proposed penalty

  17. Inspection and cover plates.

    violationRecord 5054632

    30 CFR 57.12032 · $1,320.00 proposed penalty

  18. Safety defects; examination, correction and records.

    violationRecord 5054485

    30 CFR 57.14100(c) · $209.00 proposed penalty

  19. High-pressure hose connections.

    violationRecord 5054484

    30 CFR 57.13021 · $209.00 proposed penalty

  20. Scaffolds and working platforms.

    violationRecord 5054483

    30 CFR 57.11027 · Significant and substantial (S&S) · $1,037.00 proposed penalty

  21. Combustible waste.

    violationRecord 9340071

    30 CFR 57.4104(b)(1) · $465.00 proposed penalty

  22. Underground transformer stations, combustible liquid storage and dispensing areas, pump rooms, compressor rooms, and hoist rooms.

    violationRecord 9340070

    30 CFR 57.4262 · $151.00 proposed penalty

  23. Housekeeping.

    violationRecord 9340069

    30 CFR 57.20003(a) · Significant and substantial (S&S) · $1,550.00 proposed penalty

  24. Protection for openings around travelways.

    violationRecord 9340068

    30 CFR 57.11012 · Significant and substantial (S&S) · $3,448.00 proposed penalty

  25. Safe access.

    violationRecord 5054631

    30 CFR 57.11001 · $432.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.