South Fort Meade Mine safety activity
MSHA violations, accident reports and inspections.
Safety activity
Insulation and fittings for power wires and cables.
30 CFR 56.12008 · $288.00 proposed penalty
Examination of working places.
30 CFR 56.18002(a) · $245.00 proposed penalty
Safe access.
30 CFR 56.11001 · $245.00 proposed penalty
Combustible waste.
30 CFR 56.4104(b) · $151.00 proposed penalty
Insulation and fittings for power wires and cables.
30 CFR 56.12008 · $165.00 proposed penalty
Handrails and toeboards.
30 CFR 56.11002 · $151.00 proposed penalty
Protection of gas cylinder valves.
30 CFR 56.16006 · $151.00 proposed penalty
Securing gas cylinders.
30 CFR 56.16005 · $151.00 proposed penalty
Safety defects; examination, correction and records.
30 CFR 56.14100(b) · $151.00 proposed penalty
Protection for openings around travelways.
30 CFR 56.11012 · $151.00 proposed penalty
Securing movable parts.
30 CFR 56.14206(b) · $151.00 proposed penalty
Temporary, portable containers.
30 CFR 47.44(b) · $151.00 proposed penalty
Housekeeping.
30 CFR 56.20003(a) · $151.00 proposed penalty
Regular Safety and Health Inspection
132.0 on-site hours reported
Verbal Hazard Complaint Inspections
3.3 on-site hours reported
Spot Inspection
3.5 on-site hours reported
Warning signs.
30 CFR 56.4101 · $151.00 proposed penalty
Parking procedures for unattended equipment.
30 CFR 56.14207 · $151.00 proposed penalty
Impoundment Spot Inspection
7.0 on-site hours reported
Verbal Hazard Complaint Inspections
8.5 on-site hours reported
Safe access.
30 CFR 56.11001 · $165.00 proposed penalty
Safety defects; examination, correction and records.
30 CFR 56.14100(b) · $151.00 proposed penalty
Impoundment Spot Inspection
11.0 on-site hours reported
Identification of power switches.
30 CFR 56.12018 · $165.00 proposed penalty
Spillage and leakage.
30 CFR 56.4102 · $165.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.