Robena Preparation Plant safety activity
MSHA violations, accident reports and inspections.
Safety activity
Electric equipment; examination, testing, and maintenance.
30 CFR 77.502 · $288.00 proposed penalty
Electric wiring and equipment; installation and maintenance.
30 CFR 77.516 · $151.00 proposed penalty
Electric wiring and equipment; installation and maintenance.
30 CFR 77.516 · $288.00 proposed penalty
Regular Safety and Health Inspection
51.5 on-site hours reported
Regular Safety and Health Inspection
45.0 on-site hours reported
Machinery
Dys awy frm wrk & restrctd act
Accident narrative
Employee was tightening a centerline cable for a dredge boat. Weather was clear temperature around 70 degrees Fahrenheit. As the employee was gaining tension on the centerline cable, the sideline cable the centerline was attached to was released due to a clamp failure. This caused the centerline cable and associated puller to strike the affected employee in the left leg.
Regular Safety and Health Inspection
25.0 on-site hours reported
Electric equipment; examination, testing, and maintenance.
30 CFR 77.502 · $151.00 proposed penalty
Regular Safety and Health Inspection
22.0 on-site hours reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.