ROAD FORK #52 MINE safety activity
MSHA violations, accident reports and inspections.
Safety activity
Inspection of fire suppression devices.
30 CFR 75.1107-16(b) · $151.00 proposed penalty
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S) · $3,448.00 proposed penalty
Storage of liquefied and nonliquefied compressed gas cylinders; requirements.
30 CFR 75.1106-3(a)(2) · $336.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · $549.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · $592.00 proposed penalty
Electric equipment; examination, testing and maintenance.
30 CFR 75.512 · $288.00 proposed penalty
Electrical connections or splices; suitability.
30 CFR 75.514 · $336.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · $549.00 proposed penalty
Electric equipment; examination, testing and maintenance.
30 CFR 75.512 · $642.00 proposed penalty
Methane monitors.
30 CFR 75.342(a)(4) · $313.00 proposed penalty
Condition and examination of firefighting equipment.
30 CFR 75.1100-3 · $398.00 proposed penalty
Preshift examination at fixed intervals.
30 CFR 75.360(f) · $226.00 proposed penalty
Roof bolting.
30 CFR 75.204(c)(1) · $336.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $3,736.00 proposed penalty
Accumulation of combustible materials.
30 CFR 75.400 · $697.00 proposed penalty
Self-rescue devices; inspection, testing, maintenance, repair, and recordkeeping.
30 CFR 75.1714-3(a) · $504.00 proposed penalty
Handtools (nonpowered)
No dys awy frm wrk,no rstr act
Accident narrative
Employee was striking a claw hammer with another claw hammer in an attempt to pull a belt pin from a mechanical splice, when a piece of metal broke off and struck their right forearm, resulting in a laceration and four sutures.
Spot Inspections
103(i) · 4.5 on-site hours reported
Automatic emergency-parking brakes.
30 CFR 75.523-3(c)(2) · $151.00 proposed penalty
Electric equipment; examination, testing and maintenance.
30 CFR 75.512 · $165.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · $245.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $366.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · $755.00 proposed penalty
Grounding metallic frames, casings, and other enclosures of electric equipment.
30 CFR 75.701 · $336.00 proposed penalty
Electric equipment; examination, testing and maintenance.
30 CFR 75.512 · Significant and substantial (S&S) · $9,757.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.