Plumstead Materials safety activity
MSHA violations, accident reports and inspections.
Safety activity
Electrical conductors.
30 CFR 56.12004 · $151.00 proposed penalty
Electrical conductors.
30 CFR 56.12004 · $151.00 proposed penalty
Grounding circuit enclosures.
30 CFR 56.12025 · $151.00 proposed penalty
Regular Safety and Health Inspection
27.3 on-site hours reported
Safety defects; examination, correction and records.
30 CFR 56.14100(b) · $151.00 proposed penalty
Housekeeping.
30 CFR 56.20003(a) · $151.00 proposed penalty
Housekeeping.
30 CFR 56.20003(a) · $151.00 proposed penalty
Trimming stockpile and muckpile faces.
30 CFR 56.9314 · Significant and substantial (S&S) · $1,968.00 proposed penalty
Berms or guardrails.
30 CFR 56.9300(a) · $398.00 proposed penalty
Parking procedures for unattended equipment.
30 CFR 56.14207 · $226.00 proposed penalty
Machinery
All other cases (incl 1st aid)
Accident narrative
EE got burnt while cutting a bolt with a torch.
Exploding vessels under pressure
Days away from work only
Accident narrative
EE opened an air line to bleed the system and forgot to turn off a ball valve at the air tank causing the air line that runs under the building to come up and out of the hole and hit EE in the head.
Regular Safety and Health Inspection
14.5 on-site hours reported
Handling of materials
All other cases (incl 1st aid)
Accident narrative
EE hurt EE's wrist shoveling under a conveyor.
Housekeeping.
30 CFR 56.20003(a) · $151.00 proposed penalty
Handrails and toeboards.
30 CFR 56.11002 · $151.00 proposed penalty
Regular Safety and Health Inspection
15.8 on-site hours reported
Operators stations.
30 CFR 56.14103(c)(1) · Significant and substantial (S&S) · $177.00 proposed penalty
Handrails and toeboards.
30 CFR 56.11002 · $151.00 proposed penalty
Horns and backup alarms.
30 CFR 56.14132(a) · Significant and substantial (S&S) · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.