  1. Automatic fire sensor and warning device systems; installation; minimum requirements.

    violationRecord 5092704

    30 CFR 75.1103-4(a)(1)(i) · $151.00 proposed penalty

  2. Accumulation of combustible materials.

    violationRecord 5092703

    30 CFR 75.400 · Significant and substantial (S&S) · $1,818.00 proposed penalty

  3. Accumulation of combustible materials.

    violationRecord 5092702

    30 CFR 75.400 · $366.00 proposed penalty

  4. Maintenance of belt conveyors and belt conveyor entries.

    violationRecord 5020756

    30 CFR 75.1731(a) · $193.00 proposed penalty

  5. Ventilation controls.

    violationRecord 5020755

    30 CFR 75.333(e)(1)(ii) · $151.00 proposed penalty

  6. Roof control plan.

    violationRecord 5020754

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  7. Communications.

    violationRecord 5092701

    30 CFR 75.1600 · $151.00 proposed penalty

  8. Ventilation controls.

    violationRecord 9849765

    30 CFR 75.333(c)(1) · $193.00 proposed penalty

  9. Mine ventilation plan; submission and approval.

    violationRecord 9849739

    30 CFR 75.370(a)(1) · $465.00 proposed penalty

  10. Automatic fire sensor and warning device systems; installation; minimum requirements.

    violationRecord 5097414

    30 CFR 75.1103-4(a)(1)(i) · $336.00 proposed penalty

  11. Mine ventilation plan; submission and approval.

    violationRecord 5097413

    30 CFR 75.370(a)(1) · $193.00 proposed penalty

  12. Ventilation controls.

    violationRecord 5020753

    30 CFR 75.333(c)(3) · $151.00 proposed penalty

  13. Accumulation of combustible materials.

    violationRecord 5020752

    30 CFR 75.400 · $549.00 proposed penalty

  14. Quantity and location of firefighting equipment.

    violationRecord 5020751

    30 CFR 75.1100-2(f) · $193.00 proposed penalty

  15. Roof control plan.

    violationRecord 5020750

    30 CFR 75.220(a)(1) · $313.00 proposed penalty

  16. Automatic fire sensors.

    violationRecord 5020749

    30 CFR 75.1103-1(b) · $193.00 proposed penalty

  17. Approval of other fire suppression devices.

    violationRecord 5020748

    30 CFR 75.1107-13(g) · $151.00 proposed penalty

  18. Protection from falls of roof, face and ribs.

    violationRecord 5092698

    30 CFR 75.202(a) · Significant and substantial (S&S) · $1,968.00 proposed penalty

  19. Mine ventilation plan; submission and approval.

    violationRecord 5092697

    30 CFR 75.370(a)(1) · Significant and substantial (S&S) · $3,184.00 proposed penalty

  20. Protection of trailing cables.

    violationRecord 5092696

    30 CFR 75.606 · $151.00 proposed penalty

  21. Mine ventilation plan; submission and approval.

    violationRecord 5020747

    30 CFR 75.370(a)(1) · $432.00 proposed penalty

  22. Accumulation of combustible materials.

    violationRecord 5020746

    30 CFR 75.400 · $366.00 proposed penalty

  23. Methane monitors.

    violationRecord 5020745

    30 CFR 75.342(a)(4) · $151.00 proposed penalty

  24. Immediate notification.

    violationRecord 9554303

    30 CFR 50.10(b) · $7,555.00 proposed penalty

  25. Roof control plan.

    violationRecord 9554302

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.