No 4 Mine safety activity
MSHA violations, accident reports and inspections.
Safety activity
Roof control plan.
30 CFR 75.220(a)(1) · $245.00 proposed penalty
Short circuit protection of trailing cables.
30 CFR 75.601 · Significant and substantial (S&S) · $1,431.00 proposed penalty
Spot Inspections
103(i) · 4.5 on-site hours reported
Fire suppression systems for diesel-powered equipment and fuel transportation units.
30 CFR 75.1911(a)(1) · $959.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · Significant and substantial (S&S) · $1,818.00 proposed penalty
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $1,431.00 proposed penalty
Drill dust control at underground areas of underground mines.
30 CFR 72.630(b) · Significant and substantial (S&S) · $2,133.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $313.00 proposed penalty
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $1,431.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · $549.00 proposed penalty
Emergency tethers.
30 CFR 75.1714-6 · Significant and substantial (S&S) · $1,431.00 proposed penalty
Criteria—Self-propelled personnel carriers.
30 CFR 75.1403-6(b)(1) · $288.00 proposed penalty
Other safeguards.
30 CFR 75.1403 · $336.00 proposed penalty
Roof control plan.
30 CFR 75.220(a)(1) · $549.00 proposed penalty
Maintenance of diesel-powered equipment.
30 CFR 75.1914(a) · $288.00 proposed penalty
Accumulation of combustible materials.
30 CFR 75.400 · $592.00 proposed penalty
Ventilation controls.
30 CFR 75.333(h) · $313.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(b) · $288.00 proposed penalty
Spot Inspections
103(i) · 11.8 on-site hours reported
Roof control plan.
30 CFR 75.220(a)(1) · Significant and substantial (S&S) · $2,712.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $313.00 proposed penalty
Nonpermissible diesel-powered equipment; design and performance requirements.
30 CFR 75.1909(j)(2) · Significant and substantial (S&S) · $1,431.00 proposed penalty
Maintenance of diesel-powered equipment.
30 CFR 75.1914(f) · $288.00 proposed penalty
Maintenance of diesel-powered equipment.
30 CFR 75.1914(a) · $288.00 proposed penalty
Nonpermissible diesel-powered equipment; electrical system design and performance requirements.
30 CFR 75.1910(f) · $288.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.