No 4 Mine safety activity
MSHA violations, accident reports and inspections.
Safety activity
Roof control plan.
30 CFR 75.220(a)(1) · Significant and substantial (S&S)
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1)
Spot Inspections
103(i) · 0.0 on-site hours reported
Permissible electric face equipment; maintenance.
30 CFR 75.503 · Significant and substantial (S&S)
Machinery and equipment; operation and maintenance.
30 CFR 75.1725(a)
Roof control plan.
30 CFR 75.220(a)(1) · Significant and substantial (S&S)
Self-rescue devices; inspection, testing, maintenance, repair, and recordkeeping.
30 CFR 75.1714-3(a)
Spot Inspections
103(i) · 9.8 on-site hours reported
Impoundment Spot Inspection
0.0 on-site hours reported
Permissible electric face equipment; maintenance.
30 CFR 75.503 · Significant and substantial (S&S)
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1)
Electric equipment; examination, testing and maintenance.
30 CFR 75.512
Other safeguards.
30 CFR 75.1403
Spot Inspections
103(i) · 7.0 on-site hours reported
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S)
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S)
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S)
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S)
Spot Inspections
103(i) · 4.0 on-site hours reported
Methane monitors.
30 CFR 75.342(a)(4)
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(a)
Accumulation of combustible materials.
30 CFR 75.400
Handling of materials
Days away from work only
Accident narrative
Employee was handling/throwing belt structure at the Longwall tailpiece when the belt rail from the structure fell and struck their left hand causing a laceration and a fracture to their left-hand little (pinky) finger.
Self-rescue devices; inspection, testing, maintenance, repair, and recordkeeping.
30 CFR 75.1714-3(a)
Roof bolting.
30 CFR 75.204(c)(1)
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.