LONGVIEW MINE safety activity
MSHA violations, accident reports and inspections.
Safety activity
Spot Inspections
103(i) · 7.5 on-site hours reported
Health Technical Investigation
7.3 on-site hours reported
Spot Inspection
6.0 on-site hours reported
Spot Inspections
103(i) · 7.5 on-site hours reported
Spot Inspections
103(i) · 8.0 on-site hours reported
Escapeways; bituminous and lignite mines.
30 CFR 75.380(d)(7)(vii)(B) · $549.00 proposed penalty
Spot Inspections
103(i) · 8.0 on-site hours reported
Accumulation of combustible materials.
30 CFR 75.400 · $151.00 proposed penalty
Respiratory equipment; gas, dusts, fumes, or mists.
30 CFR 72.701 · $151.00 proposed penalty
Spot Inspections
103(i) · 7.0 on-site hours reported
Roof control plan.
30 CFR 75.220(a)(1) · $177.00 proposed penalty
Spot Inspections
103(i) · 7.5 on-site hours reported
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · $245.00 proposed penalty
Electrical Technical Investigation
5.0 on-site hours reported
Spot Inspections
103(i) · 8.0 on-site hours reported
Roof control plan.
30 CFR 75.220(a)(1) · $151.00 proposed penalty
Accumulation of combustible materials.
30 CFR 75.400 · $267.00 proposed penalty
Spot Inspections
103(i) · 5.0 on-site hours reported
Sampling; general and technical requirements.
30 CFR 70.201(c) · $193.00 proposed penalty
Spot Inspections
103(i) · 4.5 on-site hours reported
Maintenance of incombustible content of rock dust.
30 CFR 75.403 · $151.00 proposed penalty
Hoisting
Accident only
Accident narrative
The personnel hoist was down for a period of time greater than 30 minutes due to a door switch/wiring issue at the shaft bottom.
Inspection and cover plates.
30 CFR 77.512 · $151.00 proposed penalty
Spot Inspections
103(i) · 8.0 on-site hours reported
Roof control plan.
30 CFR 75.220(a)(1) · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.