Safety activity
Electric equipment and circuits; overload and short circuit protection.
30 CFR 75.518 · $336.00 proposed penalty
Refuge alternatives.
30 CFR 75.1506(f)(1) · $58,171.00 proposed penalty
Mechanical equipment guards.
30 CFR 75.1722(a) · $336.00 proposed penalty
Machinery and equipment; operation and maintenance.
30 CFR 75.1725(a) · Significant and substantial (S&S) · $755.00 proposed penalty
Automatic emergency-parking brakes.
30 CFR 75.523-3(c)(2) · $151.00 proposed penalty
Accumulation of combustible materials.
30 CFR 75.400 · $432.00 proposed penalty
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $1,126.00 proposed penalty
Refuge alternatives.
30 CFR 75.1506(f) · $52,353.00 proposed penalty
Inspection of fire suppression devices.
30 CFR 75.1107-16(b) · $151.00 proposed penalty
Accumulation of combustible materials.
30 CFR 75.400 · $959.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $2,936.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · $366.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · $366.00 proposed penalty
Drill dust control at underground areas of underground mines.
30 CFR 72.630(b) · Significant and substantial (S&S) · $2,712.00 proposed penalty
Machinery and equipment; operation and maintenance.
30 CFR 75.1725(a) · Significant and substantial (S&S) · $1,818.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $697.00 proposed penalty
Machinery and equipment; operation and maintenance.
30 CFR 75.1725(a) · Significant and substantial (S&S) · $2,503.00 proposed penalty
Automatic emergency-parking brakes.
30 CFR 75.523-3(c)(2) · $151.00 proposed penalty
Short circuit protection; ratings and settings of circuit breakers.
30 CFR 75.601-1 · $151.00 proposed penalty
Short circuit protection; ratings and settings of circuit breakers.
30 CFR 75.601-1 · $336.00 proposed penalty
Short circuit protection; ratings and settings of circuit breakers.
30 CFR 75.601-1 · $336.00 proposed penalty
Machinery and equipment; operation and maintenance.
30 CFR 75.1725(a) · Significant and substantial (S&S) · $1,679.00 proposed penalty
Spot Inspections
103(i) · 7.3 on-site hours reported
Proximity detection systems.
30 CFR 75.1732(b)(2) · $504.00 proposed penalty
Condition and examination of firefighting equipment.
30 CFR 75.1100-3 · $549.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.