← Jerry Fork Eagle

Jerry Fork Eagle safety activity

MSHA violations, accident reports and inspections.

2025-01-01 – 2026-10-31Database snapshot · 2026-10-31

Safety activity

  1. Spot Inspections

    inspectionRecord 6321747

    103(i) · 5.0 on-site hours reported

  2. Spot Inspections

    inspectionRecord F006F0E

    103(i) · 6.0 on-site hours reported

  3. Health Technical Investigation

    inspectionRecord F02EDFE

    7.0 on-site hours reported

  4. Methane monitors.

    violationRecord 5023479

    30 CFR 75.342(a)(4) · $151.00 proposed penalty

  5. Mine ventilation plan; submission and approval.

    violationRecord 5023478

    30 CFR 75.370(a)(1) · Significant and substantial (S&S) · $1,431.00 proposed penalty

  6. Spot Inspections

    inspectionRecord F02D0CD

    103(i) · 8.5 on-site hours reported

  7. Spot Inspections

    inspectionRecord F007E1B

    103(i) · 9.0 on-site hours reported

  8. Mine ventilation plan; submission and approval.

    violationRecord 5020577

    30 CFR 75.370(a)(1) · $642.00 proposed penalty

  9. Spot Inspections

    inspectionRecord F006F0D

    103(i) · 7.0 on-site hours reported

  10. Other safeguards.

    violationRecord 5023475

    30 CFR 75.1403 · $959.00 proposed penalty

  11. Methane monitors.

    violationRecord 5023474

    30 CFR 75.342(a)(4) · $151.00 proposed penalty

  12. Mine ventilation plan; submission and approval.

    violationRecord 5023473

    30 CFR 75.370(a)(1) · Significant and substantial (S&S) · $3,184.00 proposed penalty

  13. Quantity and location of firefighting equipment.

    violationRecord 5020576

    30 CFR 75.1100-2(d) · $288.00 proposed penalty

  14. Spot Inspections

    inspectionRecord F007E1A

    103(i) · 9.5 on-site hours reported

  15. Mine ventilation plan; submission and approval.

    violationRecord 5020575

    30 CFR 75.370(a)(1) · $642.00 proposed penalty

  16. Electric equipment and circuits; overload and short circuit protection.

    violationRecord 5023472

    30 CFR 75.518 · $288.00 proposed penalty

  17. Protection of trailing cables.

    violationRecord 5023471

    30 CFR 75.606 · $288.00 proposed penalty

  18. Mine ventilation plan; submission and approval.

    violationRecord 5023470

    30 CFR 75.370(a)(1) · $398.00 proposed penalty

  19. Preshift examination at fixed intervals.

    violationRecord 5020574

    30 CFR 75.360(f) · $151.00 proposed penalty

  20. Spot Inspections

    inspectionRecord F007E19

    103(i) · 8.0 on-site hours reported

  21. Accumulation of combustible materials.

    violationRecord 5023469

    30 CFR 75.400 · $549.00 proposed penalty

  22. Inspection of fire suppression devices.

    violationRecord 5023468

    30 CFR 75.1107-16(b) · $313.00 proposed penalty

  23. Mining machines, cap lamps; requirements.

    violationRecord 5023467

    30 CFR 75.1719-4(b) · $193.00 proposed penalty

  24. Permissible electric face equipment; maintenance.

    violationRecord 5023466

    30 CFR 75.503 · $465.00 proposed penalty

  25. Spot Inspections

    inspectionRecord F02D0CC

    103(i) · 6.0 on-site hours reported

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.