  1. Mine ventilation plan; submission and approval.

    violationRecord 5090509

    30 CFR 75.370(d) · $151.00 proposed penalty

  2. Escapeway maps.

    violationRecord 5090508

    30 CFR 75.1505(b) · $209.00 proposed penalty

  3. Preshift examination at fixed intervals.

    violationRecord 5090507

    30 CFR 75.360(f) · $398.00 proposed penalty

  4. Ventilation controls.

    violationRecord 5090506

    30 CFR 75.333(c) · $151.00 proposed penalty

  5. Roof control plan.

    violationRecord 5090505

    30 CFR 75.220(a)(1) · $592.00 proposed penalty

  6. Ventilation controls.

    violationRecord 5090504

    30 CFR 75.333(h) · $151.00 proposed penalty

  7. Preshift examination at fixed intervals.

    violationRecord 5090503

    30 CFR 75.360(g) · $267.00 proposed penalty

  8. Diesel equipment inventory.

    violationRecord 5090501

    30 CFR 72.520(a) · $273.00 proposed penalty

  9. Installation of electric equipment and conductors; permissibility.

    violationRecord 9838699

    30 CFR 75.1002(a) · $151.00 proposed penalty

  10. Installation of electric equipment and conductors; permissibility.

    violationRecord 5090502

    30 CFR 75.1002(a) · $151.00 proposed penalty

  11. Power wires and cables; insulation and protection.

    violationRecord 5090500

    30 CFR 75.517 · Significant and substantial (S&S) · $883.00 proposed penalty

  12. Preshift examination at fixed intervals.

    violationRecord 9838698

    30 CFR 75.360(g) · $151.00 proposed penalty

  13. Spot Inspections

    inspectionRecord F001982

    103(i) · 4.0 on-site hours reported

  14. Machinery and equipment; operation and maintenance.

    violationRecord 9838697

    30 CFR 75.1725(a) · $398.00 proposed penalty

  15. Permissible electric face equipment; maintenance.

    violationRecord 9838696

    30 CFR 75.503 · $151.00 proposed penalty

  16. Accumulation of combustible materials.

    violationRecord 9838695

    30 CFR 75.400 · $151.00 proposed penalty

  17. Power wires and cables; insulation and protection.

    violationRecord 9838694

    30 CFR 75.517 · $267.00 proposed penalty

  18. Electric equipment; examination, testing and maintenance.

    violationRecord 9838693

    30 CFR 75.512 · $151.00 proposed penalty

  19. Roof control plan.

    violationRecord 9839727

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  20. Spot Inspections

    inspectionRecord F001980

    103(i) · 4.0 on-site hours reported

  21. Drill dust control at underground areas of underground mines.

    violationRecord 9839725

    30 CFR 72.630(b) · $151.00 proposed penalty

  22. Roof control plan.

    violationRecord 9839724

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  23. Other safeguards.

    violationRecord 9838684

    30 CFR 75.1403

  24. Self-rescue devices; inspection, testing, maintenance, repair, and recordkeeping.

    violationRecord 9838690

    30 CFR 75.1714-3(a) · $398.00 proposed penalty

  25. Availability of approved self-rescue devices; instruction in use and location.

    violationRecord 9838689

    30 CFR 75.1714(a) · $398.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.