Goldrush safety activity
MSHA violations, accident reports and inspections.
Safety activity
Ground support use.
30 CFR 57.3360 · $549.00 proposed penalty
Regular Safety and Health Inspection
54.3 on-site hours reported
Refuge areas.
30 CFR 57.11052(d) · $755.00 proposed penalty
Safety defects; examination, correction and records.
30 CFR 57.14100(c) · $642.00 proposed penalty
Auxiliary fan systems.
30 CFR 57.8529 · $193.00 proposed penalty
Ground support use.
30 CFR 57.3360 · $1,037.00 proposed penalty
Correction of hazardous conditions.
30 CFR 57.3200 · $226.00 proposed penalty
High-pressure hose connections.
30 CFR 57.13021 · $151.00 proposed penalty
Examination of working places.
30 CFR 57.18002(b) · Significant and substantial (S&S) · $1,679.00 proposed penalty
Housekeeping.
30 CFR 57.20003(a) · Significant and substantial (S&S) · $1,126.00 proposed penalty
Safety defects; examination, correction and records.
30 CFR 57.14100(c) · Significant and substantial (S&S) · $3,184.00 proposed penalty
Safety defects; examination, correction and records.
30 CFR 57.14100(c) · $151.00 proposed penalty
Spillage and leakage.
30 CFR 57.4102 · $226.00 proposed penalty
Barricades and warning signs.
30 CFR 57.20011 · $151.00 proposed penalty
Ground support use.
30 CFR 57.3360 · $697.00 proposed penalty
Handling of materials
No dys awy frm wrk,no rstr act
Accident narrative
During jumbo shank replacement, the flushing head was stiff and difficult to seat. Force was applied while the employee's hand remained near the pinch point. The head slipped/shifted unexpectedly, contacting the left middle finger and causing a laceration and fracture requiring one suture.
Combustible waste.
30 CFR 57.4104(b)(2) · $151.00 proposed penalty
Regular Safety and Health Inspection
94.0 on-site hours reported
Stacking and storage of materials.
30 CFR 57.16001 · $151.00 proposed penalty
Inspection.
30 CFR 57.4201(a)(2) · $226.00 proposed penalty
First aid materials.
30 CFR 57.15001 · $165.00 proposed penalty
Verbal Hazard Complaint Inspections
2.0 on-site hours reported
Verbal Hazard Complaint Inspections
2.8 on-site hours reported
Operating speeds and control of equipment.
30 CFR 57.9101 · Significant and substantial (S&S) · $18,504.00 proposed penalty
Machinery
Days away from work only
Accident narrative
EE was sprayed by another EE with water from a water cannon. Seen at clinic, diagnosed with a contusion and on follow-up referred to PT and MRI. Released to modified duty.
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.