← Gateway North Mine

Gateway North Mine safety activity

MSHA violations, accident reports and inspections.

2025-01-01 – 2026-10-31Database snapshot · 2026-10-31

Safety activity

  1. Short circuit protection; ratings and settings of circuit breakers.

    violationRecord 9783887

    30 CFR 75.601-1 · $818.00 proposed penalty

  2. Accumulation of combustible materials.

    violationRecord 9783886

    30 CFR 75.400 · $504.00 proposed penalty

  3. Roof control plan.

    violationRecord 9781395

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  4. Roof control plan.

    violationRecord 9781555

    30 CFR 75.220(a)(1) · $883.00 proposed penalty

  5. Roof control plan.

    violationRecord 9781554

    30 CFR 75.220(a)(1) · $267.00 proposed penalty

  6. Protection from falls of roof, face and ribs.

    violationRecord 9781394

    30 CFR 75.202(a) · $1,431.00 proposed penalty

  7. Accumulation of combustible materials.

    violationRecord 9786136

    30 CFR 75.400 · $398.00 proposed penalty

  8. Accumulation of combustible materials.

    violationRecord 9786135

    30 CFR 75.400 · Significant and substantial (S&S) · $1,968.00 proposed penalty

  9. Accumulation of combustible materials.

    violationRecord 9786134

    30 CFR 75.400 · $398.00 proposed penalty

  10. Electric equipment; examination, testing and maintenance.

    violationRecord 9781553

    30 CFR 75.512 · $697.00 proposed penalty

  11. Maintenance of belt conveyors and belt conveyor entries.

    violationRecord 9783885

    30 CFR 75.1731(b) · $193.00 proposed penalty

  12. Accumulation of combustible materials.

    violationRecord 9783884

    30 CFR 75.400 · $398.00 proposed penalty

  13. Maintenance of incombustible content of rock dust.

    violationRecord 9783883

    30 CFR 75.403 · $151.00 proposed penalty

  14. Maintenance of incombustible content of rock dust.

    violationRecord 9783882

    30 CFR 75.403 · $151.00 proposed penalty

  15. Roof control plan.

    violationRecord 9783881

    30 CFR 75.220(a)(1) · $151.00 proposed penalty

  16. Accumulation of combustible materials.

    violationRecord 9783880

    30 CFR 75.400 · $398.00 proposed penalty

  17. Belt air course ventilation.

    violationRecord 9781552

    30 CFR 75.350(a)(2) · $755.00 proposed penalty

  18. Accumulation of combustible materials.

    violationRecord 9781551

    30 CFR 75.400 · $398.00 proposed penalty

  19. Roof control plan.

    violationRecord 9549735

    30 CFR 75.220(a)(1) · $398.00 proposed penalty

  20. Quarterly sampling; mechanized mining units.

    violationRecord 9541067

    30 CFR 70.208(a)(1) · $151.00 proposed penalty

  21. Protection from falls of roof, face and ribs.

    violationRecord 9781393

    30 CFR 75.202(a) · Significant and substantial (S&S) · $1,431.00 proposed penalty

  22. Escapeways; bituminous and lignite mines.

    violationRecord 9781392

    30 CFR 75.380(d)(7)(vii) · $465.00 proposed penalty

  23. Roof bolting.

    violationRecord 9781391

    30 CFR 75.204(c)(1) · $193.00 proposed penalty

  24. Nonpermissible diesel-powered equipment; electrical system design and performance requirements.

    violationRecord 9783879

    30 CFR 75.1910(a) · Significant and substantial (S&S) · $959.00 proposed penalty

  25. Mine ventilation plan; submission and approval.

    violationRecord 9781550

    30 CFR 75.370(a)(1) · $1,320.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.