← Flying Eagle

Flying Eagle safety activity

MSHA violations, accident reports and inspections.

2025-01-01 – 2026-10-31Database snapshot · 2026-10-31

Safety activity

  1. Ventilation controls.

    violationRecord 5028304

    30 CFR 75.333(d)(1) · $245.00 proposed penalty

  2. Accumulation of combustible materials.

    violationRecord 5186424

    30 CFR 75.400 · $465.00 proposed penalty

  3. Other safeguards.

    violationRecord 5186423

    30 CFR 75.1403 · $288.00 proposed penalty

  4. Accumulation of combustible materials.

    violationRecord 5186422

    30 CFR 75.400 · $465.00 proposed penalty

  5. Protection from falls of roof, face and ribs.

    violationRecord 5099356

    30 CFR 75.202(a) · $432.00 proposed penalty

  6. Escapeways; bituminous and lignite mines.

    violationRecord 5028696

    30 CFR 75.380(d)(7)(iii) · $151.00 proposed penalty

  7. Quantity and location of firefighting equipment.

    violationRecord 5020450

    30 CFR 75.1100-2(f) · $288.00 proposed penalty

  8. Other safeguards.

    violationRecord 5028300

    30 CFR 75.1403 · Significant and substantial (S&S) · $1,219.00 proposed penalty

  9. Other safeguards.

    violationRecord 5028299

    30 CFR 75.1403

  10. Protection of trailing cables.

    violationRecord 5028298

    30 CFR 75.606 · Significant and substantial (S&S) · $4,047.00 proposed penalty

  11. Protection of trailing cables.

    violationRecord 5028297

    30 CFR 75.606 · Significant and substantial (S&S) · $4,047.00 proposed penalty

  12. Machinery and equipment; operation and maintenance.

    violationRecord 5028296

    30 CFR 75.1725(a) · $366.00 proposed penalty

  13. Mine ventilation plan; submission and approval.

    violationRecord 5028295

    30 CFR 75.370(a)(1) · Significant and substantial (S&S) · $10,569.00 proposed penalty

  14. Other safeguards.

    violationRecord 5028294

    30 CFR 75.1403 · $909.00 proposed penalty

  15. Roof control plan.

    violationRecord 9840160

    30 CFR 75.220(a)(1) · $336.00 proposed penalty

  16. Roof bolting.

    violationRecord 9840159

    30 CFR 75.204(c)(1) · $151.00 proposed penalty

  17. Mine ventilation plan; submission and approval.

    violationRecord 9840158

    30 CFR 75.370(a)(1) · $432.00 proposed penalty

  18. Accumulation of combustible materials.

    violationRecord 9840157

    30 CFR 75.400 · $398.00 proposed penalty

  19. Protection from falls of roof, face and ribs.

    violationRecord 9840156

    30 CFR 75.202(a) · $549.00 proposed penalty

  20. Escapeways; bituminous and lignite mines.

    violationRecord 9840155

    30 CFR 75.380(d)(7)(vi) · $151.00 proposed penalty

  21. Protection from falls of roof, face and ribs.

    violationRecord 9840154

    30 CFR 75.202(a) · Significant and substantial (S&S) · $4,047.00 proposed penalty

  22. Highwalls, pits and spoil banks; plans.

    violationRecord 9840153

    30 CFR 77.1000 · $165.00 proposed penalty

  23. Hazardous conditions and violations of mandatory health or safety standards; posting, correcting, and recording.

    violationRecord 9840152

    30 CFR 75.363(b) · $151.00 proposed penalty

  24. Mechanical equipment guards.

    violationRecord 9840151

    30 CFR 75.1722(a) · $165.00 proposed penalty

  25. Accumulation of combustible materials.

    violationRecord 9840150

    30 CFR 75.400 · $267.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.