Excel #5 safety activity
MSHA violations, accident reports and inspections.
Safety activity
Nonpermissible diesel-powered equipment; design and performance requirements.
30 CFR 75.1909(a)(1) · $151.00 proposed penalty
Deenergization of self-propelled electric face equipment installation requirements.
30 CFR 75.523-1(a) · $151.00 proposed penalty
Spot Inspections
103(i) · 1.8 on-site hours reported
Maintenance of incombustible content of rock dust.
30 CFR 75.403 · $151.00 proposed penalty
Power wires and cables; insulation and protection.
30 CFR 75.517 · Significant and substantial (S&S) · $1,219.00 proposed penalty
Methane monitors.
30 CFR 75.342(a)(4) · $151.00 proposed penalty
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S) · $1,037.00 proposed penalty
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S) · $3,736.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(b) · $151.00 proposed penalty
Other safeguards.
30 CFR 75.1403 · $226.00 proposed penalty
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S) · $1,126.00 proposed penalty
Nonpermissible diesel-powered equipment; design and performance requirements.
30 CFR 75.1909(a)(3)(x) · $151.00 proposed penalty
Other safeguards.
30 CFR 75.1403 · $151.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(b) · $151.00 proposed penalty
Spot Inspections
103(i) · 5.5 on-site hours reported
Preshift examination at fixed intervals.
30 CFR 75.360(g) · $151.00 proposed penalty
Belt air course ventilation.
30 CFR 75.350(a)(2) · $151.00 proposed penalty
Mine ventilation plan; submission and approval.
30 CFR 75.370(a)(1) · $193.00 proposed penalty
Protection from falls of roof, face and ribs.
30 CFR 75.202(a) · Significant and substantial (S&S) · $1,126.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
30 CFR 75.1731(b) · $151.00 proposed penalty
Quantity and location of firefighting equipment.
30 CFR 75.1100-2(b) · $151.00 proposed penalty
Compliance with approved slope and shaft sinking plans.
30 CFR 77.1900-1 · $151.00 proposed penalty
Mechanical equipment guards.
30 CFR 75.1722(a) · $151.00 proposed penalty
Permissible electric face equipment; maintenance.
30 CFR 75.503 · $226.00 proposed penalty
Regular Safety and Health Inspection
430.0 on-site hours reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.