← Cinder Mountain Mine

Cinder Mountain Mine safety activity

MSHA violations, accident reports and inspections.

2025-01-01 – 2026-10-28Database snapshot · 2026-10-28

Safety activity

  1. Annual refresher training.

    violationRecord 5173849

    30 CFR 46.8(a)(2)

  2. Examination of working places.

    violationRecord 5173848

    30 CFR 56.18002(a) · Significant and substantial (S&S)

  3. Insulation and fittings for power wires and cables.

    violationRecord 5173847

    30 CFR 56.12008

  4. Inspection and cover plates.

    violationRecord 5173846

    30 CFR 56.12032

  5. Berms or guardrails.

    violationRecord 5173845

    30 CFR 56.9300(b) · Significant and substantial (S&S)

  6. Insulation and fittings for power wires and cables.

    violationRecord 5173844

    30 CFR 56.12008 · $245.00 proposed penalty

  7. Moving machine parts.

    violationRecord 5173843

    30 CFR 56.14107(a) · $151.00 proposed penalty

  8. Protection of power conductors from mobile equipment.

    violationRecord 5173842

    30 CFR 56.12005 · $288.00 proposed penalty

  9. Housekeeping.

    violationRecord 5173841

    30 CFR 56.20003(a) · $151.00 proposed penalty

  10. Examination of working places.

    violationRecord 5173840

    30 CFR 56.18002(a) · Significant and substantial (S&S)

  11. Moving machine parts.

    violationRecord 5173839

    30 CFR 56.14107(a) · $151.00 proposed penalty

  12. Moving machine parts.

    violationRecord 5173838

    30 CFR 56.14107(a) · Significant and substantial (S&S)

  13. Safety defects; examination, correction and records.

    violationRecord 5173837

    30 CFR 56.14100(a) · Significant and substantial (S&S)

  14. Safety defects; examination, correction and records.

    violationRecord 5173836

    30 CFR 56.14100(b) · Significant and substantial (S&S)

  15. Parking procedures for unattended equipment.

    violationRecord 5173835

    30 CFR 56.14207 · Significant and substantial (S&S)

  16. Regular Safety and Health Inspection

    inspectionRecord F0247B8

    15.5 on-site hours reported

  17. Verbal Hazard Complaint Inspections

    inspectionRecord F0247B2

    4.0 on-site hours reported

  18. Moving machine parts.

    violationRecord 9799596

    30 CFR 56.14107(a) · $5,277.00 proposed penalty

  19. Moving machine parts.

    violationRecord 9799595

    30 CFR 56.14107(a) · Significant and substantial (S&S) · $26,139.00 proposed penalty

  20. Moving machine parts.

    violationRecord 9799594

    30 CFR 56.14107(a) · Significant and substantial (S&S) · $26,139.00 proposed penalty

  21. Moving machine parts.

    violationRecord 9799593

    30 CFR 56.14107(a) · Significant and substantial (S&S) · $26,139.00 proposed penalty

  22. Protection for openings around travelways.

    violationRecord 9799592

    30 CFR 56.11012 · Significant and substantial (S&S) · $3,022.00 proposed penalty

  23. Moving machine parts.

    violationRecord 9799591

    30 CFR 56.14107(a) · Significant and substantial (S&S) · $26,139.00 proposed penalty

  24. Moving machine parts.

    violationRecord 9799590

    30 CFR 56.14107(a) · Significant and substantial (S&S) · $26,139.00 proposed penalty

  25. Moving machine parts.

    violationRecord 9799589

    30 CFR 56.14107(a) · Significant and substantial (S&S) · $26,139.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.