← Amrize Midlothian Plant

Amrize Midlothian Plant safety activity

MSHA violations, accident reports and inspections.

2025-01-01 – 2026-10-31Database snapshot · 2026-10-31

Safety activity

  1. Construction and maintenance of guards.

    violationRecord 9796731

    30 CFR 56.14112(a)(1) · Significant and substantial (S&S) · $883.00 proposed penalty

  2. Construction and maintenance of guards.

    violationRecord 9796730

    30 CFR 56.14112(a)(1) · Significant and substantial (S&S) · $883.00 proposed penalty

  3. Inspection.

    violationRecord 5002405

    30 CFR 56.4201(a)(1) · $177.00 proposed penalty

  4. Protection for openings around travelways.

    violationRecord 5002404

    30 CFR 56.11012 · Significant and substantial (S&S) · $883.00 proposed penalty

  5. Safe access.

    violationRecord 5002403

    30 CFR 56.11001 · Significant and substantial (S&S) · $883.00 proposed penalty

  6. Construction and maintenance of guards.

    violationRecord 5002402

    30 CFR 56.14112(a)(1) · Significant and substantial (S&S) · $1,320.00 proposed penalty

  7. Requirement for container labels.

    violationRecord 9994138

    30 CFR 47.41(a) · $177.00 proposed penalty

  8. Inspection and cover plates.

    violationRecord 9994137

    30 CFR 56.12032 · $177.00 proposed penalty

  9. Inspection and cover plates.

    violationRecord 9994136

    30 CFR 56.12032 · $177.00 proposed penalty

  10. Requirement for container labels.

    violationRecord 9796729

    30 CFR 47.41(a) · $177.00 proposed penalty

  11. First-aid materials.

    violationRecord 9796728

    30 CFR 56.15001 · $151.00 proposed penalty

  12. Requirement for container labels.

    violationRecord 9796727

    30 CFR 47.41(a)(1) · $151.00 proposed penalty

  13. Electrical conductors.

    violationRecord 9796000

    30 CFR 56.12004 · $177.00 proposed penalty

  14. Moving machine parts.

    violationRecord 9795999

    30 CFR 56.14107(a) · $177.00 proposed penalty

  15. Inspection.

    violationRecord 9795998

    30 CFR 56.4201(a)(1) · $177.00 proposed penalty

  16. Inspection.

    violationRecord 9795997

    30 CFR 56.4201(a)(1) · $177.00 proposed penalty

  17. Electrical conductors.

    violationRecord 5002401

    30 CFR 56.12004 · $177.00 proposed penalty

  18. Regular Safety and Health Inspection

    inspectionRecord F015087

    65.5 on-site hours reported

  19. Guarding electrical connections and resistor grids.

    violationRecord 9796726

    30 CFR 56.12023 · $151.00 proposed penalty

  20. Inspection.

    violationRecord 9796725

    30 CFR 56.4201(a)(2) · $151.00 proposed penalty

  21. Handrails and toeboards.

    violationRecord 9796724

    30 CFR 56.11002 · $151.00 proposed penalty

  22. Inspection.

    violationRecord 9795996

    30 CFR 56.4201(a)(1) · $209.00 proposed penalty

  23. Electrical conductors.

    violationRecord 9795995

    30 CFR 56.12004 · $209.00 proposed penalty

  24. Testing grounding systems.

    violationRecord 9795994

    30 CFR 56.12028 · $209.00 proposed penalty

  25. Spillage and leakage.

    violationRecord 9795993

    30 CFR 56.4102 · $209.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.