← American Soda LLC

American Soda LLC safety activity

MSHA violations, accident reports and inspections.

2025-01-01 – 2026-10-31Database snapshot · 2026-10-31

Safety activity

  1. Requirement for container labels.

    violationRecord 9904889

    30 CFR 47.41(a) · $267.00 proposed penalty

  2. Electrical conductors.

    violationRecord 9904888

    30 CFR 57.12004 · $288.00 proposed penalty

  3. Housekeeping.

    violationRecord 9904887

    30 CFR 57.20003(a) · $366.00 proposed penalty

  4. Spillage and leakage.

    violationRecord 9904886

    30 CFR 57.4102 · $245.00 proposed penalty

  5. Spot Inspections

    inspectionRecord F01B32B

    103(i) · 4.3 on-site hours reported

  6. Safe access.

    violationRecord 9905406

    30 CFR 57.11001 · Significant and substantial (S&S) · $1,818.00 proposed penalty

  7. Safety defects; examination, correction and records.

    violationRecord 9905405

    30 CFR 57.14100(b) · $959.00 proposed penalty

  8. Inspection and cover plates.

    violationRecord 9905203

    30 CFR 57.12032 · $209.00 proposed penalty

  9. Moving machine parts.

    violationRecord 9905147

    30 CFR 57.14107(a) · $465.00 proposed penalty

  10. Dust control.

    violationRecord 9905146

    30 CFR 57.9315 · Significant and substantial (S&S) · $9,004.00 proposed penalty

  11. Testing grounding systems.

    violationRecord 9905404

    30 CFR 57.12028 · $818.00 proposed penalty

  12. Moving machine parts.

    violationRecord 9905145

    30 CFR 57.14107(a) · $313.00 proposed penalty

  13. Moving machine parts.

    violationRecord 9905144

    30 CFR 57.14107(a) · $313.00 proposed penalty

  14. Examination of working places.

    violationRecord 9904885

    30 CFR 57.18002(a) · Significant and substantial (S&S) · $2,712.00 proposed penalty

  15. Construction and maintenance of guards.

    violationRecord 9904884

    30 CFR 57.14112(a)(1) · Significant and substantial (S&S) · $1,968.00 proposed penalty

  16. Construction and maintenance of guards.

    violationRecord 9904883

    30 CFR 57.14112(a)(1) · $398.00 proposed penalty

  17. Construction and maintenance of guards.

    violationRecord 9904882

    30 CFR 57.14112(a)(1) · $398.00 proposed penalty

  18. Inspection.

    violationRecord 9904881

    30 CFR 57.4201(a)(1) · $313.00 proposed penalty

  19. High-pressure hose connections.

    violationRecord 9904880

    30 CFR 57.13021 · $165.00 proposed penalty

  20. Electrical conductors.

    violationRecord 9904879

    30 CFR 57.12004 · $288.00 proposed penalty

  21. Construction and maintenance of guards.

    violationRecord 9904878

    30 CFR 57.14112(a)(1) · $398.00 proposed penalty

  22. Construction and maintenance of guards.

    violationRecord 9904877

    30 CFR 57.14112(a)(1) · $398.00 proposed penalty

  23. Inspection and cover plates.

    violationRecord 9904876

    30 CFR 57.12032 · $209.00 proposed penalty

  24. Construction and maintenance of guards.

    violationRecord 9904875

    30 CFR 57.14112(a)(1) · Significant and substantial (S&S) · $1,968.00 proposed penalty

  25. Spot Inspections

    inspectionRecord F014362

    103(i) · 2.5 on-site hours reported

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.