American Asphalt - CHASE QUARRY safety activity
MSHA violations, accident reports and inspections.
Safety activity
Handrails and toeboards.
30 CFR 56.11002 · $151.00 proposed penalty
Regular Safety and Health Inspection
18.3 on-site hours reported
Impoundment Spot Inspection
6.3 on-site hours reported
Electrical conductors.
30 CFR 56.12004 · Significant and substantial (S&S) · $1,037.00 proposed penalty
Regular Safety and Health Inspection
27.5 on-site hours reported
Impoundment Spot Inspection
5.0 on-site hours reported
Compliance Follow-up Inspection
0.0 on-site hours reported
Compliance Follow-up Inspection
1.0 on-site hours reported
Spot Inspection
0.8 on-site hours reported
Violation — cited standard not reported
$168.00 proposed penalty
Special Emphasis Programs
2.5 on-site hours reported
Impoundment Spot Inspection
4.3 on-site hours reported
Splices and repairs of power cables.
30 CFR 56.12013(c) · $151.00 proposed penalty
Safety belts and lines.
30 CFR 56.15005 · Significant and substantial (S&S) · $839.00 proposed penalty
Violation — cited standard not reported
Safe access.
30 CFR 56.11001 · $193.00 proposed penalty
Splices and repairs of power cables.
30 CFR 56.12013 · $151.00 proposed penalty
Electrical conductors.
30 CFR 56.12004 · $151.00 proposed penalty
Electrical conductors.
30 CFR 56.12004 · $151.00 proposed penalty
Construction and maintenance of guards.
30 CFR 56.14112(a)(1) · $151.00 proposed penalty
Regular Safety and Health Inspection
28.5 on-site hours reported
Electrical conductors.
30 CFR 56.12004 · $151.00 proposed penalty
Berms or guardrails.
30 CFR 56.9300(b) · Significant and substantial (S&S) · $432.00 proposed penalty
Berms or guardrails.
30 CFR 56.9300(a) · $151.00 proposed penalty
Operating speeds and control of equipment.
30 CFR 56.9101 · Significant and substantial (S&S) · $2,503.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.