3M safety activity
MSHA violations, accident reports and inspections.
Safety activity
Inspection.
30 CFR 56.4201(a)(2)
Moving machine parts.
30 CFR 56.14107(a)
Regular Safety and Health Inspection
17.3 on-site hours reported
Electrical conductors.
30 CFR 56.12004
Insulation and fittings for power wires and cables.
30 CFR 56.12008
Electrical conductors.
30 CFR 56.12004
Electrical conductors.
30 CFR 56.12004
Electrical conductors.
30 CFR 56.12004
Electrical conductors.
30 CFR 56.12004
Requirement for container labels.
30 CFR 47.41(a) · $165.00 proposed penalty
Parking procedures for unattended equipment.
30 CFR 56.14207 · $6,037.00 proposed penalty
Housekeeping.
30 CFR 56.20003(a) · $366.00 proposed penalty
Construction and maintenance of guards.
30 CFR 56.14112(b) · $549.00 proposed penalty
Regular Safety and Health Inspection
17.0 on-site hours reported
Compliance Follow-up Inspection
1.0 on-site hours reported
Correction of dangerous conditions.
30 CFR 56.12030 · Significant and substantial (S&S) · $1,550.00 proposed penalty
Moving machine parts.
30 CFR 56.14107(a) · $151.00 proposed penalty
Berms or guardrails.
30 CFR 56.9300(a) · $151.00 proposed penalty
Stacking and storage of materials.
30 CFR 56.16001 · $151.00 proposed penalty
Inspection and cover plates.
30 CFR 56.12032 · Significant and substantial (S&S) · $697.00 proposed penalty
Safe access.
30 CFR 56.11001 · $151.00 proposed penalty
Regular Safety and Health Inspection
18.5 on-site hours reported
Correction of dangerous conditions.
30 CFR 56.12030 · $366.00 proposed penalty
Housekeeping.
30 CFR 56.20003(a) · Significant and substantial (S&S) · $549.00 proposed penalty
Unguarded conveyors with adjacent travelways.
30 CFR 56.14109(a) · $165.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.