Thorberg Collectorate Inc safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Loading and haulage equipment; installations.
Smith #2 · 151994530 CFR 77.1605(d) · Significant and substantial (S&S) · $151.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
Smith #2 · 151994530 CFR 77.1606(c) · $151.00 proposed penalty
Loading and haulage equipment; operation.
Smith #2 · 151994530 CFR 77.1607(i) · $151.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
Smith #2 · 151994530 CFR 77.1606(c) · Significant and substantial (S&S) · $177.00 proposed penalty
Loading and haulage equipment; operation.
Smith #2 · 151994530 CFR 77.1607(i)
Loading and haulage equipment; operation.
Smith #2 · 151994530 CFR 77.1607(i) · Significant and substantial (S&S) · $1,252.00 proposed penalty
Machinery and equipment; operation and maintenance.
Smith #2 · 151994530 CFR 77.404(a) · Significant and substantial (S&S) · $151.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
Smith #2 · 151994530 CFR 77.1606(c) · $151.00 proposed penalty
Protection from falls of roof, face and ribs.
Smith #2 · 151994530 CFR 75.202(a) · Significant and substantial (S&S) · $504.00 proposed penalty
Electric equipment; examination, testing and maintenance.
Smith #2 · 151994530 CFR 75.512 · $151.00 proposed penalty
Regular Safety and Health Inspection
Coalgood Darby 1 · 151993936.5 on-site hours reported
First-aid equipment; location; minimum requirements.
Magnum #2 · 151986930 CFR 75.1713-7(b)(10) · $151.00 proposed penalty
On-shift examination.
Magnum #2 · 151986930 CFR 75.362(g)(3) · $151.00 proposed penalty
Highwalls, pits and spoil banks; plans.
Right Fork Splint · 151842330 CFR 77.1000 · $151.00 proposed penalty
Protection of trailing cables.
Right Fork Splint · 151842330 CFR 77.604 · $151.00 proposed penalty
Loading and haulage equipment; operation.
Smith #2 · 151994530 CFR 77.1607(i) · $151.00 proposed penalty
Highwalls, pits and spoil banks; plans.
Right Fork Splint · 151842330 CFR 77.1000 · $151.00 proposed penalty
Loading and haulage equipment; inspection and maintenance.
Right Fork Splint · 151842330 CFR 77.1606(c) · $151.00 proposed penalty
Escapeways; bituminous and lignite mines.
Magnum #2 · 151986930 CFR 75.380(d)(7)(vii) · $151.00 proposed penalty
Regular Safety and Health Inspection
Right Fork Splint · 151842341.0 on-site hours reported
Regular Safety and Health Inspection
Magnum #2 · 1519869133.3 on-site hours reported
Regular Safety and Health Inspection
Smith #2 · 1519945150.3 on-site hours reported
Minimum requirements of surface bathing facilities, change rooms, and sanitary toilet facilities.
Coalgood Darby 1 · 151993930 CFR 75.1712-3(c)(1)(i) · $151.00 proposed penalty
Minimum requirements of surface bathing facilities, change rooms, and sanitary toilet facilities.
Coalgood Darby 1 · 151993930 CFR 75.1712-3(a) · $151.00 proposed penalty
Verbal Hazard Complaint Inspections
Coalgood Darby 1 · 15199395.0 on-site hours reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.