Escapeways; bituminous and lignite mines.
LONGVIEW MINE · 460944730 CFR 75.380(d)(7)(vi) · $267.00 proposed penalty
Maintenance of belt conveyors and belt conveyor entries.
LONGVIEW MINE · 460944730 CFR 75.1731(a) · $151.00 proposed penalty
Hazardous conditions and violations of mandatory health or safety standards; posting, correcting, and recording.
LONGVIEW MINE · 460944730 CFR 75.363(b) · $151.00 proposed penalty
Ventilation controls.
LONGVIEW MINE · 460944730 CFR 75.333(e)(1)(ii) · $151.00 proposed penalty
Spot Inspections
LONGVIEW MINE · 4609447103(i) · 8.0 on-site hours reported
Automatic fire sensor and warning device systems; installation; minimum requirements.
LONGVIEW MINE · 460944730 CFR 75.1103-4(a)(1)(iv) · $151.00 proposed penalty
Spot Inspections
LONGVIEW MINE · 4609447103(i) · 9.5 on-site hours reported
Travelways at surface installations.
LONGVIEW MINE · 460944730 CFR 77.205(a) · $151.00 proposed penalty
Identification of circuit breakers.
LONGVIEW MINE · 460944730 CFR 77.904 · $151.00 proposed penalty
Spot Inspections
LONGVIEW MINE · 4609447103(i) · 7.0 on-site hours reported
Roof control plan.
LONGVIEW MINE · 460944730 CFR 75.220(a)(1) · $151.00 proposed penalty
Permissible electric face equipment; maintenance.
LONGVIEW MINE · 460944730 CFR 75.503 · $151.00 proposed penalty
Permissible electric face equipment; maintenance.
LONGVIEW MINE · 460944730 CFR 75.503 · $151.00 proposed penalty
Electric equipment; examination, testing and maintenance.
LONGVIEW MINE · 460944730 CFR 75.512 · $151.00 proposed penalty
Spot Inspections
LONGVIEW MINE · 4609447103(i) · 8.3 on-site hours reported
Mine ventilation plan; submission and approval.
LONGVIEW MINE · 460944730 CFR 75.370(a)(1) · $151.00 proposed penalty
Health Technical Investigation
LONGVIEW MINE · 460944711.5 on-site hours reported
Drill dust control at underground areas of underground mines.
LONGVIEW MINE · 460944730 CFR 72.630(b) · $151.00 proposed penalty
Spot Inspections
LONGVIEW MINE · 4609447103(i) · 8.0 on-site hours reported
Rock dusting.
LONGVIEW MINE · 460944730 CFR 75.402 · $151.00 proposed penalty
Spot Inspections
LONGVIEW MINE · 4609447103(i) · 7.5 on-site hours reported
Slip or fall of person
LONGVIEW MINE · 4609447Days away from work only
Accident narrative
Employee set up a 5' step ladder to assist with hanging a bag. When they stepped up onto the first rung the left leg shifted causing them to lose balance and fall. They used their left arm to brace for the fall. Their hand struck the ground spraining their thumb. Injury was not the result of a training or compliance issue.
Spot Inspections
LONGVIEW MINE · 4609447103(i) · 9.0 on-site hours reported
Mine ventilation plan; submission and approval.
LONGVIEW MINE · 460944730 CFR 75.370(a)(1) · Significant and substantial (S&S) · $366.00 proposed penalty
Escapeway maps.
LONGVIEW MINE · 460944730 CFR 75.1505(b) · $504.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.