Sibanye Stillwater Limited safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Distribution boxes.
STILLWATER MINE · 240149030 CFR 57.12006 · $5,574.00 proposed penalty
Safe access.
STILLWATER MINE · 240149030 CFR 57.11001 · $549.00 proposed penalty
Abandoned electric circuits.
STILLWATER MINE · 240149030 CFR 57.4011 · $151.00 proposed penalty
Distribution boxes.
STILLWATER MINE · 240149030 CFR 57.12006 · $1,126.00 proposed penalty
Permissible exposure level.
STILLWATER MINE · 240149030 CFR 62.130(c) · $398.00 proposed penalty
Inspection and cover plates.
STILLWATER MINE · 240149030 CFR 57.12032 · $818.00 proposed penalty
Safe access.
STILLWATER MINE · 240149030 CFR 57.11001 · $549.00 proposed penalty
Housekeeping.
STILLWATER MINE · 240149030 CFR 57.20003(a) · Significant and substantial (S&S) · $2,503.00 proposed penalty
Spillage and leakage.
STILLWATER MINE · 240149030 CFR 57.4102 · $209.00 proposed penalty
Powered haulage
EAST BOULDER MINE · 2401879Days away from work only
Accident narrative
Miner was assisting partner in loading a pallet with a power cable on it. While guiding the 2yd operator up to the pallet, the bucket of the loader contacted the Miner's ankle, resulting in a fracture.
Electrical conductors.
STILLWATER MINE · 240149030 CFR 57.12004 · $549.00 proposed penalty
Inspection and cover plates.
STILLWATER MINE · 240149030 CFR 57.12032 · $1,818.00 proposed penalty
Testing grounding systems.
STILLWATER MINE · 240149030 CFR 57.12028 · $549.00 proposed penalty
Electrical conductors.
STILLWATER MINE · 240149030 CFR 57.12004 · $549.00 proposed penalty
Controls and switches.
STILLWATER MINE · 240149030 CFR 57.12002 · $398.00 proposed penalty
Construction and maintenance of guards.
STILLWATER MINE · 240149030 CFR 57.14112(a)(1) · $398.00 proposed penalty
Fan installations.
STILLWATER MINE · 240149030 CFR 57.4504(b) · $267.00 proposed penalty
Correction of hazardous conditions.
STILLWATER MINE · 240149030 CFR 57.3200 · $7,676.00 proposed penalty
Fan installations.
STILLWATER MINE · 240149030 CFR 57.4504(b) · $336.00 proposed penalty
Housekeeping.
STILLWATER MINE · 240149030 CFR 57.20003(a) · $592.00 proposed penalty
First aid materials.
STILLWATER MINE · 240149030 CFR 57.15001 · $313.00 proposed penalty
Safety can use.
STILLWATER MINE · 240149030 CFR 57.4402 · $313.00 proposed penalty
Testing grounding systems.
STILLWATER MINE · 240149030 CFR 57.12028 · $465.00 proposed penalty
Safe access.
STILLWATER MINE · 240149030 CFR 57.11001 · Significant and substantial (S&S) · $3,184.00 proposed penalty
Surface fan installations and mine openings.
STILLWATER MINE · 240149030 CFR 57.4131(a) · $313.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.