Mike Dean Scheffler safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Spot Inspection
Portable Secondary Plant · 21036409.0 on-site hours reported
Compliance Follow-up Inspection
Portable #1 (Red Rock Quarry) · 210345412.0 on-site hours reported
Exposure limits for airborne contaminants.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.5001(a)/.5005 · Significant and substantial (S&S) · $1,679.00 proposed penalty
Compliance Follow-up Inspection
Portable #1 (Red Rock Quarry) · 21034541.3 on-site hours reported
Spot Inspection
Portable #1 (Red Rock Quarry) · 21034542.0 on-site hours reported
103 (g) Written Notification Hazard Complaint Inspectio
Portable #1 (Red Rock Quarry) · 210345414.3 on-site hours reported
Berms or guardrails.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.9300(b) · $755.00 proposed penalty
Examination of working places.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.18002(a) · Significant and substantial (S&S) · $1,431.00 proposed penalty
Construction and maintenance of guards.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.14112(a)(1) · $226.00 proposed penalty
Safety defects; examination, correction and records.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.14100(c) · Significant and substantial (S&S) · $1,126.00 proposed penalty
Regular Safety and Health Inspection
Portable Secondary Plant · 21036405.8 on-site hours reported
Closure of valves.
Portable Secondary Plant · 210364030 CFR 56.4603(b) · $151.00 proposed penalty
Preparation and submission of MSHA Report Form 7000-1—Mine Accident, Injury, and Illness Report.
Portable #1 (Red Rock Quarry) · 210345430 CFR 50.20(a) · $151.00 proposed penalty
Examination of working places.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.18002(a) · $151.00 proposed penalty
Requirement for container labels.
Portable #1 (Red Rock Quarry) · 210345430 CFR 47.41(a) · $151.00 proposed penalty
Warning signs.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.4101 · $151.00 proposed penalty
Safe access.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.11001 · Significant and substantial (S&S) · $3,022.00 proposed penalty
Safety defects; examination, correction and records.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.14100(c) · $465.00 proposed penalty
Construction and maintenance of ladders.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.11003 · $151.00 proposed penalty
Temporary, portable containers.
Portable #1 (Red Rock Quarry) · 210345430 CFR 47.44(b) · $151.00 proposed penalty
Electrical conductors.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.12004 · $226.00 proposed penalty
Moving machine parts.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.14107(a) · $336.00 proposed penalty
Electrical conductors.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.12004 · $755.00 proposed penalty
Combustible waste.
Portable #1 (Red Rock Quarry) · 210345430 CFR 56.4104(b) · $226.00 proposed penalty
Temporary, portable containers.
Portable #1 (Red Rock Quarry) · 210345430 CFR 47.44(b) · $755.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.