← Michael Hollingshead

Michael Hollingshead safety activity

MSHA violations, accident reports and inspections across the current mine portfolio.

2025-01-01 – 2026-10-31Database snapshot · 2026-10-31

Safety activity

  1. Spot Inspection

    inspectionRecord F026707
    SRM Materials Tri County · 4000048

    4.0 on-site hours reported

  2. Spot Inspection

    inspectionRecord F046772
    Smyrna Quarry · 4003538

    14.8 on-site hours reported

  3. Impoundment Spot Inspection

    inspectionRecord F03037B
    Cleveland Quarry · 0901098

    5.8 on-site hours reported

  4. Spot Inspection

    inspectionRecord F01F675
    SRM UPTON QUARRY · 1519952

    11.3 on-site hours reported

  5. Verbal Hazard Complaint Inspections

    inspectionRecord F041D81
    Crab Orchard Quarry · 4002210

    2.5 on-site hours reported

  6. Spot Inspection

    inspectionRecord F03B791
    SRM Materials South Channing Pit · 4104785

    0.5 on-site hours reported

  7. Identification of power switches.

    violationRecord 5080291
    Crab Orchard Quarry · 4002210

    30 CFR 56.12018

  8. Parking procedures for unattended equipment.

    violationRecord 5179078
    SRM Materials South Channing Pit · 4104785

    30 CFR 56.14207

  9. New task training.

    violationRecord 5179077
    SRM Materials South Channing Pit · 4104785

    30 CFR 46.7(a) · Significant and substantial (S&S) · $76,728.00 proposed penalty

  10. Bins, hoppers, silos, tanks, and surge piles.

    violationRecord 5179072
    SRM Materials South Channing Pit · 4104785

    30 CFR 56.16002(c) · Significant and substantial (S&S)

  11. Verbal Hazard Complaint Inspections

    inspectionRecord F02B9DE
    Crab Orchard Quarry · 4002210

    3.5 on-site hours reported

  12. Training plan implementation.

    violationRecord 5080290
    Crab Orchard Quarry · 4002210

    30 CFR 46.4(a)(2)

  13. Annual refresher training.

    violationRecord 5080289
    Crab Orchard Quarry · 4002210

    30 CFR 46.8(a)

  14. Verbal Hazard Complaint Inspections

    inspectionRecord F02B9DD
    Crab Orchard Quarry · 4002210

    3.5 on-site hours reported

  15. Insulation and fittings for power wires and cables.

    violationRecord 5080288
    Crab Orchard Quarry · 4002210

    30 CFR 56.12008

  16. Testing grounding systems.

    violationRecord 5080287
    Crab Orchard Quarry · 4002210

    30 CFR 56.12028

  17. Protection of persons at switchgear.

    violationRecord 5080286
    Crab Orchard Quarry · 4002210

    30 CFR 56.12020

  18. Grounding circuit enclosures.

    violationRecord 5080070
    Crab Orchard Quarry · 4002210

    30 CFR 56.12025

  19. Grounding transformer and switchgear enclosures.

    violationRecord 5080069
    Crab Orchard Quarry · 4002210

    30 CFR 56.12026

  20. Protection of power conductors from mobile equipment.

    violationRecord 5080068
    Crab Orchard Quarry · 4002210

    30 CFR 56.12005

  21. Protection of persons at switchgear.

    violationRecord 5080067
    Crab Orchard Quarry · 4002210

    30 CFR 56.12020

  22. Requirements for written safety program.

    violationRecord 5176988
    SRM Hamilton Quarry · 4105752

    30 CFR 56.23003(b)

  23. Spot Inspection

    inspectionRecord F03DA5A
    Crab Orchard Quarry · 4002210

    0.0 on-site hours reported

  24. Spot Inspection

    inspectionRecord F03DA54
    Crab Orchard Quarry · 4002210

    29.8 on-site hours reported

  25. Regular Safety and Health Inspection

    inspectionRecord F046230
    SRM Hamilton Quarry · 4105752

    6.3 on-site hours reported

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.