Barnhart Quarry · 230246930 CFR 56.14100(b) · $151.00 proposed penalty
Inspection.
Martin Marietta - Woodville Lime & Stone · 330015630 CFR 56.4201(a)(2) · $151.00 proposed penalty
Temporary, portable containers.
Martin Marietta - Woodville Lime & Stone · 330015630 CFR 47.44(b) · $151.00 proposed penalty
Verbal Hazard Complaint Inspections
Montevallo Quarry & Mill · 01000404.0 on-site hours reported
Regular Safety and Health Inspection
Barnhart Quarry · 230246914.3 on-site hours reported
Regular Safety and Health Inspection
MAIDEN QUARRY · 31021259.0 on-site hours reported
Machinery, equipment, and tools.
Fort Myers Quarry · 080120330 CFR 56.14205 · Significant and substantial (S&S) · $151.00 proposed penalty
Electrical conductors.
Fort Myers Quarry · 080120330 CFR 56.12004 · $151.00 proposed penalty
Electrical conductors.
Fort Myers Quarry · 080120330 CFR 56.12004 · $245.00 proposed penalty
Safety defects; examination, correction and records.
Fort Myers Quarry · 080120330 CFR 56.14100(b) · $151.00 proposed penalty
Correction of hazardous conditions.
Barnhart Quarry · 230246930 CFR 56.3200 · $151.00 proposed penalty
Inspection.
Martin Marietta - Woodville Lime & Stone · 330015630 CFR 56.4201(a)(2) · $151.00 proposed penalty
Regular Safety and Health Inspection
Fort Myers Quarry · 080120319.5 on-site hours reported
Regular Safety and Health Inspection
Pedersen Quarry · 13021925.8 on-site hours reported
Regular Safety and Health Inspection
Boonsboro Quarry · 180002413.0 on-site hours reported
Regular Safety and Health Inspection
BAKERS QUARRY · 310007115.5 on-site hours reported
Inspection and cover plates.
Martin Marietta - Woodville Lime & Stone · 330015630 CFR 56.12032 · $151.00 proposed penalty
Inspection and cover plates.
Martin Marietta - Woodville Lime & Stone · 330015630 CFR 56.12032 · $151.00 proposed penalty
Electrical conductors.
Martin Marietta - Woodville Lime & Stone · 330015630 CFR 56.12004 · $151.00 proposed penalty
Handling of materials
Clifton Plant · 4100013Days restricted activity only
Accident narrative
Employee was pulling cable in upstream area and felt a pop in right shoulder when pulling back.
Construction and maintenance of ladders.
Texas Quarry · 180000930 CFR 56.11003 · $151.00 proposed penalty
Suspended loads.
Davis Quarry · 340129930 CFR 56.16009 · Significant and substantial (S&S) · $432.00 proposed penalty
Safety defects; examination, correction and records.
Davis Quarry · 340129930 CFR 56.14100(b) · $151.00 proposed penalty
Handling of materials
Yellow Medicine Quarry · 2100033Days restricted activity only
Accident narrative
Employee injured right bicep while lifting pump out of crate. Injury became reportable on July, 2nd 2026 due to restricted work.
Regular Safety and Health Inspection
YAVAPAI PLANT 22 · 020122210.8 on-site hours reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.