(Lowell) Austin Williams; Christopher C Williams safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Regular Safety and Health Inspection
Doniphan Sand & Gravel · 230256917.0 on-site hours reported
Regular Safety and Health Inspection
Van Buren Stone · 230208014.0 on-site hours reported
Verbal Hazard Complaint Inspections
Poplar Bluff Stone · 23024892.0 on-site hours reported
Construction and maintenance of guards.
Poplar Bluff Stone · 230248930 CFR 56.14112(a)(1) · $151.00 proposed penalty
Correction of dangerous conditions.
Poplar Bluff Stone · 230248930 CFR 56.12030 · $288.00 proposed penalty
Regular Safety and Health Inspection
Poplar Bluff Stone · 230248913.8 on-site hours reported
Horns and backup alarms.
Poplar Bluff Stone · 230248930 CFR 56.14132(a) · $151.00 proposed penalty
Spot Inspection
Van Buren Stone · 23020800.0 on-site hours reported
Testing grounding systems.
Doniphan Sand & Gravel · 230256930 CFR 56.12028 · $151.00 proposed penalty
Electrical conductors.
Doniphan Sand & Gravel · 230256930 CFR 56.12004 · $151.00 proposed penalty
Regular Safety and Health Inspection
Doniphan Sand & Gravel · 23025695.0 on-site hours reported
Horns and backup alarms.
Poplar Bluff Stone · 230248930 CFR 56.14132(a) · $151.00 proposed penalty
Circuit overload protection.
Poplar Bluff Stone · 230248930 CFR 56.12001 · $209.00 proposed penalty
Housekeeping.
Poplar Bluff Stone · 230248930 CFR 56.20003(a) · $209.00 proposed penalty
Unguarded conveyors with adjacent travelways.
Poplar Bluff Stone · 230248930 CFR 56.14109(b)(2) · $313.00 proposed penalty
Regular Safety and Health Inspection
Poplar Bluff Stone · 23024898.3 on-site hours reported
Regular Safety and Health Inspection
Van Buren Stone · 23020804.8 on-site hours reported
Moving machine parts.
Van Buren Stone · 230208030 CFR 56.14107(a) · $151.00 proposed penalty
Moving machine parts.
Van Buren Stone · 230208030 CFR 56.14107(a) · $151.00 proposed penalty
Moving machine parts.
Van Buren Stone · 230208030 CFR 56.14107(a) · $151.00 proposed penalty
Moving machine parts.
Van Buren Stone · 230208030 CFR 56.14107(a) · $151.00 proposed penalty
Splices and repairs of power cables.
Van Buren Stone · 230208030 CFR 56.12013 · $151.00 proposed penalty
Testing grounding systems.
Van Buren Stone · 230208030 CFR 56.12028 · $151.00 proposed penalty
Insulation and fittings for power wires and cables.
Poplar Bluff Stone · 230248930 CFR 56.12008 · $151.00 proposed penalty
Construction and maintenance of guards.
Poplar Bluff Stone · 230248930 CFR 56.14112(a)(1) · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.