Jobeco Materials LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Action level.
Avispa Canyon Quarry · 410479530 CFR 62.120 · $151.00 proposed penalty
Action level.
Avispa Canyon Quarry · 410479530 CFR 62.120 · $151.00 proposed penalty
Parking procedures for unattended equipment.
Avispa Canyon Quarry · 410479530 CFR 56.14207 · Significant and substantial (S&S) · $755.00 proposed penalty
Moving machine parts.
Avispa Canyon Quarry · 410479530 CFR 56.14107(a) · $151.00 proposed penalty
Safety defects; examination, correction and records.
Avispa Canyon Quarry · 410479530 CFR 56.14100(b) · $151.00 proposed penalty
Construction and maintenance of guards.
Avispa Canyon Quarry · 410479530 CFR 56.14112(b) · $151.00 proposed penalty
Regular Safety and Health Inspection
Avispa Canyon Quarry · 410479520.5 on-site hours reported
Action level.
Ned Finney Quarry · 410456830 CFR 62.120 · $151.00 proposed penalty
Parking procedures for unattended equipment.
Ned Finney Quarry · 410456830 CFR 56.14207 · $151.00 proposed penalty
Moving machine parts.
Ned Finney Quarry · 410456830 CFR 56.14107(a) · $151.00 proposed penalty
Regular Safety and Health Inspection
Ned Finney Quarry · 410456819.3 on-site hours reported
Regular Safety and Health Inspection
McCombs Sand Pit · 41055189.8 on-site hours reported
Compliance Follow-up Inspection
Van Horn Quarry · 41052381.0 on-site hours reported
Regular Safety and Health Inspection
Dyer Sand Pit · 410471213.0 on-site hours reported
Berms or guardrails.
Dyer Sand Pit · 410471230 CFR 56.9300(b) · $151.00 proposed penalty
Regular Safety and Health Inspection
Hitt Canyon Quarry Mine · 410467212.5 on-site hours reported
Moving machine parts.
Hitt Canyon Quarry Mine · 410467230 CFR 56.14107(a) · $151.00 proposed penalty
Moving machine parts.
Vado Quarry · 290241130 CFR 56.14107(a) · $465.00 proposed penalty
Inspection.
Vado Quarry · 290241130 CFR 56.4201(a)(2) · $1,037.00 proposed penalty
Identification of power switches.
Vado Quarry · 290241130 CFR 56.12018 · $1,037.00 proposed penalty
Housekeeping.
Vado Quarry · 290241130 CFR 56.20003(b) · Significant and substantial (S&S) · $5,144.00 proposed penalty
Berms or guardrails.
Vado Quarry · 290241130 CFR 56.9300(a) · $1,037.00 proposed penalty
Regular Safety and Health Inspection
Vado Quarry · 29024119.5 on-site hours reported
First aid.
Van Horn Quarry · 410523830 CFR 56.18010 · $151.00 proposed penalty
Regular Safety and Health Inspection
Van Horn Quarry · 41052385.8 on-site hours reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.