James Construction Group, LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Action level.
Miller Springs Materials · 410450530 CFR 62.120 · $151.00 proposed penalty
Site-specific hazard awareness training.
Miller Springs Materials · 410450530 CFR 46.11(b)(6) · $151.00 proposed penalty
Hand-held power tools.
Miller Springs Materials · 410450530 CFR 56.14116(a) · $151.00 proposed penalty
Regular Safety and Health Inspection
Miller Springs Materials · 410450516.8 on-site hours reported
Moving machine parts.
Miller Springs Materials · 410450530 CFR 56.14107(a) · $151.00 proposed penalty
Parking procedures for unattended equipment.
Miller Springs Materials · 410450530 CFR 56.14207 · $151.00 proposed penalty
Regular Safety and Health Inspection
Miller Springs Materials · 410450510.5 on-site hours reported
Waste receptacles.
Miller Springs Materials · 410450530 CFR 56.20013 · $151.00 proposed penalty
Insulation and fittings for power wires and cables.
Miller Springs Materials · 410450530 CFR 56.12008 · $151.00 proposed penalty
Moving machine parts.
Miller Springs Materials · 410450530 CFR 56.14107(a) · Significant and substantial (S&S) · $818.00 proposed penalty
Moving machine parts.
Miller Springs Materials · 410450530 CFR 56.14107(a) · Significant and substantial (S&S) · $549.00 proposed penalty
Electrical conductors.
Miller Springs Materials · 410450530 CFR 56.12004 · $151.00 proposed penalty
Electrical conductors.
Miller Springs Materials · 410450530 CFR 56.12004 · $151.00 proposed penalty
Handtools (nonpowered)
Miller Springs Materials · 4104505No dys awy frm wrk,no rstr act
Accident narrative
Mechanic was adjusting blow bar and small piece of metal flew off blow bar and struck Mechanic in chest.
Regular Safety and Health Inspection
Miller Springs Materials · 41045058.5 on-site hours reported
General instructions for completing MSHA Form 7000-1.
Miller Springs Materials · 410450530 CFR 50.20-1 · $151.00 proposed penalty
Verbal Hazard Complaint Inspections
Miller Springs Materials · 41045053.0 on-site hours reported
Compliance Follow-up Inspection
Miller Springs Materials · 41045050.0 on-site hours reported
Annual refresher training.
Miller Springs Materials · 410450530 CFR 46.8(a) · $348.00 proposed penalty
Insulation and fittings for power wires and cables.
Miller Springs Materials · 410450530 CFR 56.12008 · $151.00 proposed penalty
Moving machine parts.
Miller Springs Materials · 410450530 CFR 56.14107(a) · Significant and substantial (S&S) · $267.00 proposed penalty
Regular Safety and Health Inspection
Miller Springs Materials · 410450519.0 on-site hours reported
Powered haulage
Miller Springs Materials · 4104505Days away from work only
Accident narrative
EMPLOYEE LEFT HAND INJURY FROM CONVEYOR BELT
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.