James C Justice III safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Roof control plan.
BELCHER BRANCH · 460947430 CFR 75.220(a)(1) · $818.00 proposed penalty
Ventilation controls.
BELCHER BRANCH · 460947430 CFR 75.333(h) · $465.00 proposed penalty
Mine ventilation plan; submission and approval.
BELCHER BRANCH · 460947430 CFR 75.370(a)(1) · $1,866.00 proposed penalty
Permissible electric face equipment; maintenance.
BELCHER BRANCH · 460947430 CFR 75.503 · $549.00 proposed penalty
Inspection of fire suppression devices.
BELCHER BRANCH · 460947430 CFR 75.1107-16(b) · $245.00 proposed penalty
Accumulation of combustible materials.
BELCHER BRANCH · 460947430 CFR 75.400 · $1,968.00 proposed penalty
Permissible electric face equipment; maintenance.
BELCHER BRANCH · 460947430 CFR 75.503 · $549.00 proposed penalty
Escapeway maps.
BELCHER BRANCH · 460947430 CFR 75.1505(b) · $1,431.00 proposed penalty
Machinery and equipment; operation and maintenance.
BELCHER BRANCH · 460947430 CFR 75.1725(a) · Significant and substantial (S&S) · $20,560.00 proposed penalty
Installation of electric equipment and conductors; permissibility.
BELCHER BRANCH · 460947430 CFR 75.1002(a) · $245.00 proposed penalty
Automatic fire sensor and warning device systems; installation; minimum requirements.
BELCHER BRANCH · 460947430 CFR 75.1103-4(b) · $959.00 proposed penalty
Communications facilities; refuge alternatives.
BELCHER BRANCH · 460947430 CFR 75.1600-3(a)(1) · $959.00 proposed penalty
Mine ventilation plan; submission and approval.
BELCHER BRANCH · 460947430 CFR 75.370(d) · $504.00 proposed penalty
Quarterly sampling; mechanized mining units.
BELCHER BRANCH · 460947430 CFR 70.208(a)(2) · $1,320.00 proposed penalty
Quarterly sampling; mechanized mining units.
BELCHER BRANCH · 460947430 CFR 70.208(a)(1) · $818.00 proposed penalty
Quarterly sampling; mechanized mining units.
BELCHER BRANCH · 460947430 CFR 70.208(a)(2) · $1,320.00 proposed penalty
Quarterly sampling; designated areas.
BELCHER BRANCH · 460947430 CFR 70.209(a) · $818.00 proposed penalty
Spot Inspections
BELCHER BRANCH · 4609474103(i) · 8.8 on-site hours reported
Weekly examination.
BELCHER BRANCH · 460947430 CFR 75.364(h) · $151.00 proposed penalty
Escapeways; bituminous and lignite mines.
BELCHER BRANCH · 460947430 CFR 75.380(d)(7) · Significant and substantial (S&S) · $4,749.00 proposed penalty
Roof control plan.
BELCHER BRANCH · 460947430 CFR 75.220(a)(1) · Significant and substantial (S&S) · $9,004.00 proposed penalty
Communication facilities; working sections; installation and maintenance requirements; audible or visual alarms.
BELCHER BRANCH · 460947430 CFR 75.1600-2(e) · $504.00 proposed penalty
Ventilation controls.
BELCHER BRANCH · 460947430 CFR 75.333(c)(3) · $549.00 proposed penalty
Roof control plan.
BELCHER BRANCH · 460947430 CFR 75.220(a)(1) · $1,818.00 proposed penalty
Protection from falls of roof, face and ribs.
BELCHER BRANCH · 460947430 CFR 75.202(a) · Significant and substantial (S&S) · $7,084.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.