← Intrepid Potash Inc

Intrepid Potash Inc safety activity

MSHA violations, accident reports and inspections across the current mine portfolio.

2025-01-01 – 2026-10-31Database snapshot · 2026-10-31

Safety activity

  1. Safety defects; examination, correction and records.

    violationRecord 5001479
    Intrepid Potash East · 2900170

    30 CFR 57.14100(b) · $151.00 proposed penalty

  2. Protection for openings around travelways.

    violationRecord 5001478
    Intrepid Potash East · 2900170

    30 CFR 57.11012 · $151.00 proposed penalty

  3. Electrical conductors.

    violationRecord 9796095
    Intrepid Potash East · 2900170

    30 CFR 57.12004 · $432.00 proposed penalty

  4. Construction and maintenance of guards.

    violationRecord 9796094
    Intrepid Potash East · 2900170

    30 CFR 57.14112(b) · $165.00 proposed penalty

  5. First aid materials.

    violationRecord 5003008
    Intrepid Potash East · 2900170

    30 CFR 57.15001 · $151.00 proposed penalty

  6. Securing movable parts.

    violationRecord 5003007
    Intrepid Potash East · 2900170

    30 CFR 57.14206(b) · $165.00 proposed penalty

  7. Inspection and cover plates.

    violationRecord 5003006
    Intrepid Potash East · 2900170

    30 CFR 57.12032 · $151.00 proposed penalty

  8. Operators' stations.

    violationRecord 5003005
    Intrepid Potash East · 2900170

    30 CFR 57.14103(b) · $151.00 proposed penalty

  9. Protection of gas cylinder valves.

    violationRecord 5003004
    Intrepid Potash East · 2900170

    30 CFR 57.16006 · $151.00 proposed penalty

  10. Inspection.

    violationRecord 5003003
    Intrepid Potash East · 2900170

    30 CFR 57.4201(a)(2) · $151.00 proposed penalty

  11. Inspection.

    violationRecord 5003002
    Intrepid Potash East · 2900170

    30 CFR 57.4201(a)(2) · $151.00 proposed penalty

  12. Correction of hazardous conditions.

    violationRecord 9797676
    Intrepid Potash East · 2900170

    30 CFR 57.3200 · Significant and substantial (S&S) · $1,219.00 proposed penalty

  13. Correction of hazardous conditions.

    violationRecord 9797675
    Intrepid Potash East · 2900170

    30 CFR 57.3200 · Significant and substantial (S&S) · $1,219.00 proposed penalty

  14. Eye protection.

    violationRecord 9797674
    Intrepid Potash East · 2900170

    30 CFR 57.15004 · $245.00 proposed penalty

  15. Construction and maintenance of guards.

    violationRecord 5001476
    Intrepid Potash East · 2900170

    30 CFR 57.14112(b) · $245.00 proposed penalty

  16. High-pressure hose connections.

    violationRecord 5001477
    Intrepid Potash West · 2900175

    30 CFR 57.13021 · $151.00 proposed penalty

  17. Regular Safety and Health Inspection

    inspectionRecord F012400
    Intrepid Potash East · 2900170

    98.5 on-site hours reported

  18. Regular Safety and Health Inspection

    inspectionRecord F012401
    Intrepid Potash West · 2900175

    8.3 on-site hours reported

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.