HBM Holdings Company safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Spot Inspection
MLC - Verona · 15191820.0 on-site hours reported
Electrical conductors.
MLC - Ste. Genevieve · 230054230 CFR 57.12004 · $1,679.00 proposed penalty
Handling of materials
MLC - Ste. Genevieve · 2300542Days away from work only
Accident narrative
Employee was attempting to close the maintenance gate on the silo when they felt a pop in their elbow. Employee declined medical treatment until 07/31/2026. On 08/11/2026, it was discovered that the employee had ligament tears in their elbow.
Brakes.
MLC - Ste. Genevieve · 230054230 CFR 57.14101(a)(2) · $398.00 proposed penalty
Safety defects; examination, correction and records.
MLC - Ste. Genevieve · 230054230 CFR 57.14100(c) · Significant and substantial (S&S) · $1,126.00 proposed penalty
Compliance Follow-up Inspection
MLC - Bonne Terre · 23023713.5 on-site hours reported
Safety defects; examination, correction and records.
MLC - Ste. Genevieve · 230054230 CFR 57.14100(b) · Significant and substantial (S&S) · $2,712.00 proposed penalty
Insulation and fittings for power wires and cables.
MLC - Ste. Genevieve · 230054230 CFR 57.12008 · $755.00 proposed penalty
Protection for openings around travelways.
MLC - Ste. Genevieve · 230054230 CFR 57.11012 · $336.00 proposed penalty
Electrical conductors.
MLC - Ste. Genevieve · 230054230 CFR 57.12004 · $226.00 proposed penalty
Electrical conductors.
MLC - Ste. Genevieve · 230054230 CFR 57.12004 · $226.00 proposed penalty
Construction and maintenance of guards.
MLC - Ste. Genevieve · 230054230 CFR 57.14112(a)(1) · $336.00 proposed penalty
Parking procedures for unattended equipment.
MLC - Ste. Genevieve · 230054230 CFR 57.14207 · $193.00 proposed penalty
Powder chests.
MLC - Ste. Genevieve · 230054230 CFR 57.6133(a)(1) · $193.00 proposed penalty
Verbal Hazard Complaint Inspections
MLC - Bonne Terre · 23023714.0 on-site hours reported
Electrical conductors.
MLC - Ste. Genevieve · 230054230 CFR 57.12004 · $1,219.00 proposed penalty
Electrical conductors.
MLC - Ste. Genevieve · 230054230 CFR 57.12004 · $1,219.00 proposed penalty
Inspection and cover plates.
MLC - Ste. Genevieve · 230054230 CFR 57.12032 · Significant and substantial (S&S) · $3,184.00 proposed penalty
Housekeeping.
MLC - Ste. Genevieve · 230054230 CFR 57.20003(a) · $755.00 proposed penalty
Moving machine parts.
MLC - Ste. Genevieve · 230054230 CFR 57.14107(a) · $1,320.00 proposed penalty
Housekeeping.
MLC - Ste. Genevieve · 230054230 CFR 57.20003(a) · $755.00 proposed penalty
Protection of gas cylinder valves.
MLC - Ste. Genevieve · 230054230 CFR 57.16006 · $193.00 proposed penalty
Safety defects; examination, correction and records.
MLC - Ste. Genevieve · 230054230 CFR 57.14100(b) · $193.00 proposed penalty
Housekeeping.
MLC - Ste. Genevieve · 230054230 CFR 57.20003(a) · $959.00 proposed penalty
Access to stationary electrical equipment or switchgear.
MLC - Ste. Genevieve · 230054230 CFR 57.12019 · $226.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.