GCC SAB de CV safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
High-pressure hose connections.
Pueblo Plant & Quarry · 050482230 CFR 56.13021 · $592.00 proposed penalty
Regular Safety and Health Inspection
Pueblo Plant & Quarry · 0504822106.0 on-site hours reported
Unguarded conveyors with adjacent travelways.
Pueblo Plant & Quarry · 050482230 CFR 56.14109(a) · $151.00 proposed penalty
Berms or guardrails.
Pueblo Plant & Quarry · 050482230 CFR 56.9300(a) · Significant and substantial (S&S) · $1,037.00 proposed penalty
Moving machine parts.
Pueblo Plant & Quarry · 050482230 CFR 56.14107(a) · $151.00 proposed penalty
Construction and maintenance of guards.
Pueblo Plant & Quarry · 050482230 CFR 56.14112(b) · $151.00 proposed penalty
Construction and maintenance of guards.
Pueblo Plant & Quarry · 050482230 CFR 56.14112(a)(1) · $313.00 proposed penalty
Stationary grinding machines.
Pueblo Plant & Quarry · 050482230 CFR 56.14115(b) · $209.00 proposed penalty
Testing grounding systems.
Pueblo Plant & Quarry · 050482230 CFR 56.12028 · $818.00 proposed penalty
Regular Safety and Health Inspection
EAST LOOP 375 SAND PLT · 41038166.8 on-site hours reported
Power wires and cables; insulation and protection.
King II · 050486430 CFR 75.517 · $193.00 proposed penalty
Berms or guardrails.
EAST LOOP 375 SAND PLT · 410381630 CFR 56.9300(a) · $151.00 proposed penalty
Moving machine parts.
EAST LOOP 375 SAND PLT · 410381630 CFR 56.14107(a) · $151.00 proposed penalty
Regular Safety and Health Inspection
King II · 0504864248.5 on-site hours reported
Handtools (nonpowered)
GCC Dacotah Inc · 3900022Dys awy frm wrk & restrctd act
Accident narrative
The employee chose a 4-foot pry bar instead of a 6-foot pry bar to open a valve on a silo pump. The employee strained and felt a pop in their shoulder.
Fall of roof or back
King II · 0504864Accident only
Accident narrative
2 NSM XC4, 7 Entry. A roof fall occurred and was found by a weekly mine examiner. Approx. 27 feet long x 17' wide. The fall was above the 7' bolt anchorage zone.
Non-Injury Accident Investigation
King II · 050486417.5 on-site hours reported
Protection from falls of roof, face and ribs.
King II · 050486430 CFR 75.202(a) · $288.00 proposed penalty
Violation — cited standard not reported
King II · 0504864Examination of working places.
GCC Dacotah Inc · 390002230 CFR 56.18002(a) · $1,550.00 proposed penalty
Stepping or kneeling on object
Odessa Cement Plant · 4100060Days restricted activity only
Accident narrative
While exiting a man lift the employee stepped on a impact and twisted right ankle.
Grounding circuit enclosures.
GCC Dacotah Inc · 390002230 CFR 56.12025 · Significant and substantial (S&S) · $17,082.00 proposed penalty
Immediate notification.
GCC Dacotah Inc · 390002230 CFR 50.10(b) · $7,555.00 proposed penalty
Water sprinkler systems; fire warning devices at belt drives.
King II · 050486430 CFR 75.1101-10 · $193.00 proposed penalty
Records of training.
GCC Dacotah Inc · 390002230 CFR 46.9(b)(5) · $465.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.