Foresight Energy Labor LLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Accumulation of combustible materials.
MC#1 Mine · 110318930 CFR 75.400 · $313.00 proposed penalty
Nonpermissible diesel-powered equipment; electrical system design and performance requirements.
Mach #1 Mine · 110314130 CFR 75.1910(d) · $245.00 proposed penalty
Mine ventilation plan; submission and approval.
MC#1 Mine · 110318930 CFR 75.370(a)(1) · Significant and substantial (S&S) · $1,818.00 proposed penalty
Handling of materials
Mach #1 Mine · 1103141Days away from work only
Accident narrative
I.E. was recovering belt structure when they felt a pop and pain in right shoulder.
Slip or fall of person
MC#1 Mine · 1103189Days away from work only
Accident narrative
I.E. stated they were stepping off of the platform backwards, their left foot was on the ground and their right foot hung on the 5-inch lip on the edge of the platform. I.E. fell backwards hitting their back on the foot of the ATRS. X-rays show a fracture in their L2.
Roof control plan.
Mach #1 Mine · 110314130 CFR 75.220(a)(1) · $267.00 proposed penalty
Accumulation of combustible materials.
Deer Run Mine · 110318230 CFR 75.400 · $267.00 proposed penalty
Spot Inspections
Mach #1 Mine · 1103141103(i) · 7.3 on-site hours reported
Mine ventilation plan; submission and approval.
Mach #1 Mine · 110314130 CFR 75.370(a)(1) · $398.00 proposed penalty
Nonpermissible diesel-powered equipment; design and performance requirements.
Mach #1 Mine · 110314130 CFR 75.1909(a)(1) · $245.00 proposed penalty
Other safeguards.
Mach #1 Mine · 110314130 CFR 75.1403 · Significant and substantial (S&S) · $1,219.00 proposed penalty
Handling of materials
Mach #1 Mine · 1103141Days away from work only
Accident narrative
I.E was building cribs in HG 17 bleeder near a regulator and felt something get blown into their eye.
Spot Inspections
MC#1 Mine · 1103189103(i) · 7.0 on-site hours reported
Machinery and equipment; operation and maintenance.
Deer Run Mine · 110318230 CFR 75.1725(a) · $226.00 proposed penalty
Installation of electric equipment and conductors; permissibility.
Deer Run Mine · 110318230 CFR 75.1002(a) · $193.00 proposed penalty
Installation of electric equipment and conductors; permissibility.
Deer Run Mine · 110318230 CFR 75.1002(a) · $193.00 proposed penalty
Permissible electric face equipment; maintenance.
MC#1 Mine · 110318930 CFR 75.503 · $245.00 proposed penalty
Nonpermissible diesel-powered equipment; electrical system design and performance requirements.
MC#1 Mine · 110318930 CFR 75.1910(j) · $193.00 proposed penalty
Power wires and cables; insulation and protection.
Deer Run Mine · 110318230 CFR 75.517 · Significant and substantial (S&S) · $3,736.00 proposed penalty
Spot Inspections
Mach #1 Mine · 1103141103(i) · 8.0 on-site hours reported
Mine ventilation plan; submission and approval.
Mach #1 Mine · 110314130 CFR 75.370(a)(1) · $504.00 proposed penalty
Mine ventilation plan; submission and approval.
Mach #1 Mine · 110314130 CFR 75.370(a)(1) · $398.00 proposed penalty
Accumulation of combustible materials.
Mach #1 Mine · 110314130 CFR 75.400 · $465.00 proposed penalty
Insulating mats at power switches.
Mach #1 Mine · 110314130 CFR 77.513 · $818.00 proposed penalty
Handling of materials
MC#1 Mine · 1103189Days away from work only
Accident narrative
I.E. stated they were dragging a tube from P.C. area to 2 left when they felt a pull in left shoulder. I.E. took themselves to the hospital for C.T. scan, waiting on results.
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.