Energy Fuels Inc safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Brakes.
White Mesa Mill · 420142930 CFR 56.14101(a)(2) · $151.00 proposed penalty
Correction of dangerous conditions.
White Mesa Mill · 420142930 CFR 56.12030 · $151.00 proposed penalty
Regular Safety and Health Inspection
White Mesa Mill · 420142931.0 on-site hours reported
Escape and evacuation plans.
PINYON PLAIN MINE · 020330530 CFR 57.11053 · $151.00 proposed penalty
Requirement for container labels.
PINYON PLAIN MINE · 020330530 CFR 47.41(a) · $151.00 proposed penalty
Regular Safety and Health Inspection
PINYON PLAIN MINE · 020330543.5 on-site hours reported
Compliance Follow-up Inspection
PINYON PLAIN MINE · 020330511.3 on-site hours reported
Permissible exposure level.
PINYON PLAIN MINE · 020330530 CFR 62.130(a) · $151.00 proposed penalty
Permissible exposure level.
PINYON PLAIN MINE · 020330530 CFR 62.130(a) · $151.00 proposed penalty
Construction and maintenance of ladders.
PINYON PLAIN MINE · 020330530 CFR 57.11003 · $151.00 proposed penalty
Loading, blasting, and security.
PINYON PLAIN MINE · 020330530 CFR 57.6306(e) · $151.00 proposed penalty
Correction of hazardous conditions.
PINYON PLAIN MINE · 020330530 CFR 57.3200 · $151.00 proposed penalty
Correction of hazardous conditions.
PINYON PLAIN MINE · 020330530 CFR 57.3200 · Significant and substantial (S&S) · $151.00 proposed penalty
Regular Safety and Health Inspection
PINYON PLAIN MINE · 020330541.5 on-site hours reported
Annual refresher training of miners; minimum courses of instruction; hours of instruction.
White Mesa Mill · 420142930 CFR 48.28(a) · $168.00 proposed penalty
Regular Safety and Health Inspection
White Mesa Mill · 420142925.0 on-site hours reported
Correction of dangerous conditions.
White Mesa Mill · 420142930 CFR 56.12030 · $151.00 proposed penalty
Identification of power switches.
White Mesa Mill · 420142930 CFR 56.12018 · $151.00 proposed penalty
Special Emphasis Programs
White Mesa Mill · 42014291.0 on-site hours reported
Procedures for inspection, testing, and maintenance.
PINYON PLAIN MINE · 020330530 CFR 57.19120 · $151.00 proposed penalty
Escape routes.
PINYON PLAIN MINE · 020330530 CFR 57.11051(a) · Significant and substantial (S&S) · $165.00 proposed penalty
Escape routes.
PINYON PLAIN MINE · 020330530 CFR 57.11051(a) · Significant and substantial (S&S) · $165.00 proposed penalty
Construction and maintenance of ladders.
PINYON PLAIN MINE · 020330530 CFR 57.11003 · $151.00 proposed penalty
Inspection.
PINYON PLAIN MINE · 020330530 CFR 57.4201(a)(5) · $151.00 proposed penalty
Grounding transformer and switchgear enclosures.
PINYON PLAIN MINE · 020330530 CFR 57.12026 · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.