Moving machine parts.
North Powder Quarry Crusher #1 · 350334530 CFR 56.14107(a) · $1,431.00 proposed penalty
Housekeeping.
North Powder Quarry Crusher #1 · 350334530 CFR 56.20003(c) · Significant and substantial (S&S) · $959.00 proposed penalty
Handrails and toeboards.
North Powder Quarry Crusher #1 · 350334530 CFR 56.11002 · $193.00 proposed penalty
Horns and backup alarms.
North Powder Quarry Crusher #1 · 350334530 CFR 56.14132(b)(1)(i) · $288.00 proposed penalty
Horns and backup alarms.
North Powder Quarry Crusher #1 · 350334530 CFR 56.14132(a) · $288.00 proposed penalty
Regular Safety and Health Inspection
Pardo Quarry · 26022923.5 on-site hours reported
Spillage and leakage.
Pardo Quarry · 260229230 CFR 56.4102 · $151.00 proposed penalty
Safety defects; examination, correction and records.
Pardo Quarry · 260229230 CFR 56.14100(b) · $151.00 proposed penalty
Construction and maintenance of guards.
North Powder Quarry Crusher #1 · 350334530 CFR 56.14112(b) · $4,749.00 proposed penalty
Construction and maintenance of guards.
North Powder Quarry Crusher #1 · 350334530 CFR 56.14112(b) · $288.00 proposed penalty
Verbal Hazard Complaint Inspections
North Powder Quarry Crusher #1 · 35033457.8 on-site hours reported
Special Emphasis Programs
Pardo Quarry · 26022921.0 on-site hours reported
Regular Safety and Health Inspection
Pardo Quarry · 26022923.0 on-site hours reported
Requirement for container labels.
Pardo Quarry · 260229230 CFR 47.41(a)(1) · $151.00 proposed penalty
Compliance Follow-up Inspection
North Powder Quarry Crusher #1 · 35033453.5 on-site hours reported
Safe access.
North Powder Quarry Crusher #1 · 350334530 CFR 56.11001 · $151.00 proposed penalty
Housekeeping.
North Powder Quarry Crusher #1 · 350334530 CFR 56.20003(a) · $151.00 proposed penalty
Electrical conductors.
North Powder Quarry Crusher #1 · 350334530 CFR 56.12004 · $267.00 proposed penalty
Moving machine parts.
North Powder Quarry Crusher #1 · 350334530 CFR 56.14107(a) · $151.00 proposed penalty
Moving machine parts.
North Powder Quarry Crusher #1 · 350334530 CFR 56.14107(a) · $151.00 proposed penalty
Moving machine parts.
North Powder Quarry Crusher #1 · 350334530 CFR 56.14107(a) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
North Powder Quarry Crusher #1 · 350334530 CFR 50.30(a) · $151.00 proposed penalty
Regular Safety and Health Inspection
North Powder Quarry Crusher #1 · 35033459.5 on-site hours reported
103 (g) Written Notification Hazard Complaint Inspectio
North Powder Quarry Crusher #1 · 35033454.8 on-site hours reported
Insulation and fittings for power wires and cables.
North Powder Quarry Crusher #1 · 350334530 CFR 56.12008 · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.