Housekeeping.
Durkee Cement Plant · 350297030 CFR 56.20003(a) · Significant and substantial (S&S) · $755.00 proposed penalty
Safe access.
Durkee Cement Plant · 350297030 CFR 56.11001 · $151.00 proposed penalty
Safe access.
Durkee Cement Plant · 350297030 CFR 56.11001 · $151.00 proposed penalty
Correction of hazardous conditions.
NEW HAVEN CRUSHED STONE C600 · 430018530 CFR 56.3200 · Significant and substantial (S&S) · $1,037.00 proposed penalty
Regular Safety and Health Inspection
Arkhola Dredge & Plant · 030037913.3 on-site hours reported
Regular Safety and Health Inspection
Portable #2 Plant 1400 · 03019217.0 on-site hours reported
Impoundment Spot Inspection
Shelly Material Inc. Ostrander · 33001684.5 on-site hours reported
Electrical conductors.
Arkhola Dredge & Plant · 030037930 CFR 56.12004 · $151.00 proposed penalty
Unguarded conveyors with adjacent travelways.
Fultonham Plant · 330004230 CFR 57.14109 · $151.00 proposed penalty
Housekeeping.
Fultonham Plant · 330004230 CFR 57.20003(a) · Significant and substantial (S&S) · $432.00 proposed penalty
Parking procedures for unattended equipment.
MARBLE CLIFF QUARRY · 330009730 CFR 57.14207 · $151.00 proposed penalty
Housekeeping.
MARBLE CLIFF QUARRY · 330009730 CFR 57.20003(a) · $209.00 proposed penalty
Housekeeping.
MARBLE CLIFF QUARRY · 330009730 CFR 57.20003(a) · $209.00 proposed penalty
Construction and maintenance of guards.
Durkee Cement Plant · 350297030 CFR 56.14112(a) · $226.00 proposed penalty
Housekeeping.
Durkee Cement Plant · 350297030 CFR 56.20003(a) · $151.00 proposed penalty
Explosive material storage practices.
Durkee Cement Plant · 350297030 CFR 56.6102(a)(3) · Significant and substantial (S&S) · $1,679.00 proposed penalty
Construction and maintenance of guards.
Durkee Cement Plant · 350297030 CFR 56.14112(a)(1) · $226.00 proposed penalty
Construction and maintenance of guards.
Durkee Cement Plant · 350297030 CFR 56.14112(a)(1) · $226.00 proposed penalty
Construction and maintenance of guards.
Durkee Cement Plant · 350297030 CFR 56.14112(a)(1) · $226.00 proposed penalty
Housekeeping.
Durkee Cement Plant · 350297030 CFR 56.20003(a) · $151.00 proposed penalty
First aid materials.
Thomasville Mine · 360343230 CFR 57.15001 · $151.00 proposed penalty
Safe access.
Thomasville Mine · 360343230 CFR 57.11001 · $151.00 proposed penalty
Parking procedures for unattended equipment.
Thomasville Mine · 360343230 CFR 57.14207 · $504.00 proposed penalty
Requirement for container labels.
Thomasville Mine · 360343230 CFR 47.41(a) · $151.00 proposed penalty
Access to stationary electrical equipment or switchgear.
Thomasville Mine · 360343230 CFR 57.12019 · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.