← CRH PLC

CRH PLC safety activity

MSHA violations, accident reports and inspections across the current mine portfolio.

2025-01-01 – 2026-10-31Database snapshot · 2026-10-31

Safety activity

  1. Safety defects; examination, correction and records.

    violationRecord 9998156
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.14100(b) · $818.00 proposed penalty

  2. Safety defects; examination, correction and records.

    violationRecord 9998155
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.14100(b) · $818.00 proposed penalty

  3. Construction and maintenance of guards.

    violationRecord 9998154
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.14112(b) · $151.00 proposed penalty

  4. Protection of persons at switchgear.

    violationRecord 9766720
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.12020 · $245.00 proposed penalty

  5. Housekeeping.

    violationRecord 9766719
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.20003(a) · $549.00 proposed penalty

  6. Warning signs.

    violationRecord 9766718
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.4101 · $165.00 proposed penalty

  7. Housekeeping.

    violationRecord 9766717
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.20003(a) · $549.00 proposed penalty

  8. Machinery, equipment, and tools.

    violationRecord 9766716
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.14205 · $549.00 proposed penalty

  9. Dropping materials from overhead.

    violationRecord 9766469
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.16010 · Significant and substantial (S&S) · $366.00 proposed penalty

  10. Moving machine parts.

    violationRecord 9766154
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.14107(a) · $245.00 proposed penalty

  11. Safety defects; examination, correction and records.

    violationRecord 9766153
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.14100(b) · $165.00 proposed penalty

  12. Safety defects; examination, correction and records.

    violationRecord 9766152
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.14100(b) · $245.00 proposed penalty

  13. Danger signs.

    violationRecord 9766151
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.12021 · $549.00 proposed penalty

  14. Housekeeping.

    violationRecord 9766150
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.20003(a) · $165.00 proposed penalty

  15. Safe access.

    violationRecord 9766149
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.11001 · $165.00 proposed penalty

  16. Safe access.

    violationRecord 5003835
    Roberts Quarry · 3401130

    30 CFR 56.11001 · $151.00 proposed penalty

  17. Identification of power switches.

    violationRecord 9793758
    Rosevine Quarry · 4104676

    30 CFR 56.12018 · $151.00 proposed penalty

  18. Regular Safety and Health Inspection

    inspectionRecord F004EA5
    Somerset Stone Company · 1500094

    18.5 on-site hours reported

  19. Regular Safety and Health Inspection

    inspectionRecord F021823
    Dracut Plant · 1900007

    4.0 on-site hours reported

  20. Regular Safety and Health Inspection

    inspectionRecord F0230DE
    COXBURG SAND & GRAVEL · 2200740

    5.0 on-site hours reported

  21. 103 (g) Written Notification Hazard Complaint Inspectio

    inspectionRecord F01877C
    Hunter Cement Plant · 4102820

    2.5 on-site hours reported

  22. Regular Safety and Health Inspection

    inspectionRecord 6321949
    Beckley Plant · 4605147

    34.5 on-site hours reported

  23. Testing grounding systems.

    violationRecord 9759652
    Warren County Quarry · 0901204

    30 CFR 56.12028 · $151.00 proposed penalty

  24. Operators and chemicals covered; initial miner training.

    violationRecord 9998153
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 47.2(b) · Significant and substantial (S&S) · $1,037.00 proposed penalty

  25. Electrical conductors.

    violationRecord 9766715
    Louisville Plant Quarry & Mill · 2500002

    30 CFR 56.12004 · $549.00 proposed penalty

Sources and definitions

MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).

Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.

Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.

Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.

Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.

S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.

Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.

Portfolio totals use current mine membership, including events before the current owner or operator's tenure.