CRH PLC safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Securing movable parts.
Portable Crusher 133 · 100132630 CFR 56.14206(b) · $151.00 proposed penalty
Use of compressed air.
00972 · 210295930 CFR 56.13020 · $151.00 proposed penalty
Electrical conductors.
Harrisonville Quarry · 230114830 CFR 56.12004 · $151.00 proposed penalty
Safety defects; examination, correction and records.
Harrisonville Quarry · 230114830 CFR 56.14100(b) · $151.00 proposed penalty
Danger signs.
Harrisonville Quarry · 230114830 CFR 56.12021 · $151.00 proposed penalty
Requirement for container labels.
GOSHEN QUARRY · 300003830 CFR 47.41(a) · $151.00 proposed penalty
Electrical conductors.
Ash Grove Tooele Plant · 420272530 CFR 56.12004 · $226.00 proposed penalty
Inspection and cover plates.
Ash Grove Tooele Plant · 420272530 CFR 56.12032 · $151.00 proposed penalty
Requirement for container labels.
Ash Grove Tooele Plant · 420272530 CFR 47.41(a) · $151.00 proposed penalty
Regular Safety and Health Inspection
Portable Crusher # 5 · 05050417.5 on-site hours reported
Regular Safety and Health Inspection
Portable Crusher 133 · 100132617.5 on-site hours reported
Spot Inspection
Lake Cumberland Stone · 15000994.0 on-site hours reported
Regular Safety and Health Inspection
SCOOTER MINE / Krystal · 22008326.3 on-site hours reported
Regular Safety and Health Inspection
Harrisonville Quarry · 23011489.8 on-site hours reported
Regular Safety and Health Inspection
GOSHEN QUARRY · 30000385.0 on-site hours reported
Regular Safety and Health Inspection
East Quarry · 340005020.3 on-site hours reported
Mine Idle Activity
Grubbs Quarry · 35039680.3 on-site hours reported
Regular Safety and Health Inspection
Ash Grove Tooele Plant · 42027255.5 on-site hours reported
Regular Safety and Health Inspection
Glade Stone Plant · 440016442.5 on-site hours reported
Mine Idle Activity
Spring St Quarry C606 · 17007941.3 on-site hours reported
Regular Safety and Health Inspection
Crusher C654 · 17010364.0 on-site hours reported
Regular Safety and Health Inspection
Stoneco Finlay Plant · 20035873.8 on-site hours reported
Powered haulage
Ottawa Lake Quarry · 2000041Days restricted activity only
Accident narrative
Traveling between stockpiles to load customer trucks, employee traveled over a pile of stone placed in the yard to prevent customer trucks from traveling over a soft area and becoming stuck. The employee was jostled around and struck the right side of EE's head against the cab window breaking out the window, cutting EE's head and contracting an abrasion to the right cornea.
Handling of materials
Boehler Pit · 2600429Dys awy frm wrk & restrctd act
Accident narrative
EE was trying to clean the metal off of the magnet that leads to the VSI. They grabbed a piece of metal to pull off and strained their arm.
Special Emphasis Programs
RiverBend Materials Turner South · 35010020.8 on-site hours reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.