Claudett Espinoza; Juan Diosdado safety activity
MSHA violations, accident reports and inspections across the current mine portfolio.
Safety activity
Eye protection.
Lueders 3 · 410549930 CFR 56.15004 · Significant and substantial (S&S) · $1,968.00 proposed penalty
Regular Safety and Health Inspection
San Saba Quarry · 41054314.0 on-site hours reported
Protective footwear.
San Saba Quarry · 410543130 CFR 56.15003 · $245.00 proposed penalty
Construction and maintenance of guards.
San Saba Quarry · 410543130 CFR 56.14112(b) · Significant and substantial (S&S) · $1,818.00 proposed penalty
Containers for hazardous materials.
San Saba Quarry · 410543130 CFR 56.16004 · $366.00 proposed penalty
Brakes.
San Saba Quarry · 410543130 CFR 56.14101(a)(2) · Significant and substantial (S&S) · $1,818.00 proposed penalty
Horns and backup alarms.
San Saba Quarry · 410543130 CFR 56.14132(b)(1)(i) · Significant and substantial (S&S) · $4,047.00 proposed penalty
Regular Safety and Health Inspection
Imperial Products Supply Granbury · 41046400.0 on-site hours reported
First-aid materials.
Imperial Products Supply Granbury · 410464030 CFR 56.15001 · $151.00 proposed penalty
Stationary grinding machines.
Imperial Products Supply Granbury · 410464030 CFR 56.14115(b) · $151.00 proposed penalty
Requirement for container labels.
Imperial Products Supply Granbury · 410464030 CFR 47.41(a) · $151.00 proposed penalty
Controls and switches.
San Saba Quarry · 410543130 CFR 56.12002 · $245.00 proposed penalty
Safety can use.
San Saba Quarry · 410543130 CFR 56.4402 · $245.00 proposed penalty
Regular Safety and Health Inspection
San Saba Quarry · 41054315.3 on-site hours reported
Compliance Follow-up Inspection
Lueders 3 · 41054990.0 on-site hours reported
Regular Safety and Health Inspection
Lueders 3 · 410549911.0 on-site hours reported
Newly hired experienced miner training.
Lueders 3 · 410549930 CFR 46.6(b) · $168.00 proposed penalty
Moving machine parts.
Lueders 3 · 410549930 CFR 56.14107(a) · Significant and substantial (S&S) · $288.00 proposed penalty
Inspection and cover plates.
Lueders 3 · 410549930 CFR 56.12032 · $151.00 proposed penalty
Scaffolds and working platforms.
Lueders 3 · 410549930 CFR 56.11027 · Significant and substantial (S&S) · $288.00 proposed penalty
Moving machine parts.
Lueders 3 · 410549930 CFR 56.14107(a) · Significant and substantial (S&S) · $288.00 proposed penalty
Spillage and leakage.
Lueders 3 · 410549930 CFR 56.4102 · $151.00 proposed penalty
Electric substations and liquid storage facilities.
Lueders 3 · 410549930 CFR 56.4130(a)(2) · $151.00 proposed penalty
Compliance Follow-up Inspection
Lueders 3 · 41054990.8 on-site hours reported
Regular Safety and Health Inspection
Imperial Products Supply Granbury · 41046402.0 on-site hours reported
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.