Compliance Follow-up Inspection
Brooksville South Cement Plant · 08012870.0 on-site hours reported
Grounding circuit enclosures.
Balcones Plant · 410288530 CFR 56.12025
Examination of working places.
Balcones Plant · 410288530 CFR 56.18002(a)(1) · Significant and substantial (S&S)
Protection for openings around travelways.
Balcones Plant · 410288530 CFR 56.11012 · Significant and substantial (S&S)
Spot Inspection
Victorville Cement Plant · 04002817.0 on-site hours reported
Spot Inspection
Brooksville Quarry · 080002412.0 on-site hours reported
Compliance Follow-up Inspection
Four Corners Sand Mine · 08014700.5 on-site hours reported
Compliance Follow-up Inspection
Ponce Cement Plant · 54000013.0 on-site hours reported
Handling of materials
Victorville Cement Plant · 0400281No dys awy frm wrk,no rstr act
Accident narrative
While opening a slide gate on a weigh feeder hopper, the gate came out of the housing and dropped onto the weigh feeder. As the employee attempted to remove EE's hand from the area, one finger became caught between the gate and the housing, resulting in an injury to the fingertip.
Spot Inspection
Clinchfield Plant · 09000532.0 on-site hours reported
Training plan implementation.
Four Corners Sand Mine · 080147030 CFR 46.4(a)(3) · Significant and substantial (S&S)
Housekeeping.
Balcones Plant · 410288530 CFR 56.20003(b)
Safe access.
Balcones Plant · 410288530 CFR 56.11001 · Significant and substantial (S&S)
Housekeeping.
Balcones Plant · 410288530 CFR 56.20003(a)
Regular Safety and Health Inspection
Four Corners Sand Mine · 080147019.5 on-site hours reported
Inspection and cover plates.
Balcones Plant · 410288530 CFR 56.12032
Correction of dangerous conditions.
Balcones Plant · 410288530 CFR 56.12030
Regular Safety and Health Inspection
Lake Wales Sand Mine · 080126917.8 on-site hours reported
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Redlands Quarry · 040486930 CFR 50.30(a) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Redlands Quarry · 040486930 CFR 50.30(a) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Redlands Quarry · 040486930 CFR 50.30(a) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Redlands Quarry · 040486930 CFR 50.30(a) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Redlands Quarry · 040486930 CFR 50.30(a) · $151.00 proposed penalty
Grounding transformer and switchgear enclosures.
Lake Wales Sand Mine · 080126930 CFR 56.12026
Control of exposure to airborne contaminants.
Brooksville South Cement Plant · 080128730 CFR 56.5005
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.