Berms or guardrails.
Blum Quarry · 410388230 CFR 56.9300(a) · $151.00 proposed penalty
Impoundment Spot Inspection
Brooksville Quarry · 08000242.5 on-site hours reported
Compliance Follow-up Inspection
Rockfield Plant · 04018978.5 on-site hours reported
Verbal Hazard Complaint Inspections
Brooksville South Cement Plant · 080128713.5 on-site hours reported
Non-Injury Accident Investigation
Lyons Cement Plant Cemex Inc · 05003441.0 on-site hours reported
Regular Safety and Health Inspection
PALMDALE SAND MINE · 08012166.8 on-site hours reported
Examination of working places.
PALMDALE SAND MINE · 080121630 CFR 56.18002(b) · $151.00 proposed penalty
Inspection.
PALMDALE SAND MINE · 080121630 CFR 56.4201(a)(1) · $151.00 proposed penalty
Changes; notification by operator.
PALMDALE SAND MINE · 080121630 CFR 41.12 · $151.00 proposed penalty
Poisoning (toxic materials)
Brooksville South Cement Plant · 0801287Occupatnal illness not deg 1-6
Accident narrative
Miner while doing material removal at ground level of Finish Mill 2 building, employee reported shortness of breath and throat felt like it was closing off. EE was wearing a dust mask N95 together with a neck gaiter.
Newly hired experienced miner training.
Demopolis Plant Cemex Inc · 010001630 CFR 46.6 · Significant and substantial (S&S) · $407.00 proposed penalty
Controls and switches.
Demopolis Plant Cemex Inc · 010001630 CFR 56.12002 · $151.00 proposed penalty
Unguarded conveyors with adjacent travelways.
Demopolis Plant Cemex Inc · 010001630 CFR 56.14109(a) · $267.00 proposed penalty
Moving machine parts.
Demopolis Plant Cemex Inc · 010001630 CFR 56.14107(a) · $267.00 proposed penalty
Access to stationary electrical equipment or switchgear.
Demopolis Plant Cemex Inc · 010001630 CFR 56.12019 · $177.00 proposed penalty
Safety defects; examination, correction and records.
Demopolis Plant Cemex Inc · 010001630 CFR 56.14100(c) · $267.00 proposed penalty
Brakes.
Demopolis Plant Cemex Inc · 010001630 CFR 56.14101(a)(3) · $313.00 proposed penalty
Other
Demopolis Plant Cemex Inc · 0100016Days restricted activity only
Accident narrative
Employee was entering a silo by way of a work platform and as EE entered the silo EE heard a pop in EE's left knee.
Regular Safety and Health Inspection
Demopolis Plant Cemex Inc · 010001623.5 on-site hours reported
Regular Safety and Health Inspection
BRIERFIELD · 01035396.0 on-site hours reported
Impoundment Spot Inspection
Cache Creek Quarry · 04027631.8 on-site hours reported
Regular Safety and Health Inspection
Dames Point Terminal · 08013754.0 on-site hours reported
Testing grounding systems.
ALICO ROAD QUARRY · 080007830 CFR 56.12028 · $209.00 proposed penalty
Construction and maintenance of guards.
ALICO ROAD QUARRY · 080007830 CFR 56.14112(b) · $151.00 proposed penalty
Housekeeping.
ALICO ROAD QUARRY · 080007830 CFR 56.20003(a) · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.