Amrize Stringtown Quarry · 340005630 CFR 56.14100(b) · $1,818.00 proposed penalty
Construction and maintenance of guards.
Amrize Portland Plant · 050003730 CFR 56.14112(a)(1) · $2,133.00 proposed penalty
Moving machine parts.
Amrize Portland Plant · 050003730 CFR 56.14107(a)
Construction and maintenance of guards.
Amrize Portland Plant · 050003730 CFR 56.14112(a)(1) · $2,133.00 proposed penalty
Examination of working places.
Amrize Portland Plant · 050003730 CFR 56.18002(a) · Significant and substantial (S&S) · $14,557.00 proposed penalty
Housekeeping.
Amrize Portland Plant · 050003730 CFR 56.20003(a) · $8,315.00 proposed penalty
Insulation and fittings for power wires and cables.
Amrize Portland Plant · 050003730 CFR 56.12008 · $883.00 proposed penalty
General requirements.
Amrize Portland Plant · 050003730 CFR 56.4200(b)(2) · $883.00 proposed penalty
Parking procedures for unattended equipment.
Amrize Portland Plant · 050003730 CFR 56.14207 · $1,968.00 proposed penalty
Warning signs.
Amrize Portland Plant · 050003730 CFR 56.4101 · $1,968.00 proposed penalty
Requirement for container labels.
Amrize Portland Plant · 050003730 CFR 47.41(a) · $1,968.00 proposed penalty
First-aid materials.
Amrize Portland Plant · 050003730 CFR 56.15001 · Significant and substantial (S&S) · $4,383.00 proposed penalty
Storage of hazardous materials.
Amrize Portland Plant · 050003730 CFR 56.16003 · $592.00 proposed penalty
Check-in, check-out system.
Amrize Conco Western Stone · 110293130 CFR 57.11058 · $267.00 proposed penalty
Warning signs.
Amrize Conco Western Stone · 110293130 CFR 57.4101 · $151.00 proposed penalty
Escape routes.
Amrize Conco Western Stone · 110293130 CFR 57.11051(b) · $288.00 proposed penalty
Protection of persons at switchgear.
Amrize Hagerstown Facility · 180001930 CFR 56.12020 · Significant and substantial (S&S) · $1,037.00 proposed penalty
Construction and maintenance of guards.
Amrize Hagerstown Facility · 180001930 CFR 56.14112(a)(1) · $151.00 proposed penalty
Safety defects; examination, correction and records.
Amrize Hagerstown Facility · 180001930 CFR 56.14100(b) · Significant and substantial (S&S) · $2,312.00 proposed penalty
Horns and backup alarms.
Amrize Stringtown Quarry · 340005630 CFR 56.14132(a) · Significant and substantial (S&S) · $2,712.00 proposed penalty
Roll-over protective structures (ROPS) and seat belts.
Amrize Stringtown Quarry · 340005630 CFR 56.14130(g) · Significant and substantial (S&S) · $1,219.00 proposed penalty
Safety defects; examination, correction and records.
Amrize Stringtown Quarry · 340005630 CFR 56.14100(b) · $549.00 proposed penalty
Horns and backup alarms.
Amrize Stringtown Quarry · 340005630 CFR 56.14132(a) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Amrize Stringtown Quarry · 340005630 CFR 50.30(a) · $151.00 proposed penalty
Preparation and submission of MSHA Form 7000-2—Quarterly Employment and Coal Production Report.
Amrize Stringtown Quarry · 340005630 CFR 50.30(a) · $151.00 proposed penalty
Sources and definitions
MSHA Violations (issue date), Accidents (accident date) and Inspections (begin date).
Violation titles use current CFR headings to identify the cited rule; they are not the inspector’s account of what happened.
Status is from the current MSHA Mines snapshot, not the selected reporting period. Closed records can retain their last reported controller/operator.
Counts describe published rows, including contractor records; accident records are not distinct incidents or numbers of people injured.
Zero means no matching records in the imported sources, not proof of no events. Historical coverage differs by source; absence before a source begins reporting is not a zero incident rate. Invalid or absent dates and records after the snapshot are excluded.
S&S means SIG_SUB=Y. Fatality records use DEGREE_INJURY_CD=01. Proposed penalties are not final assessed or paid amounts; missing dollar values are omitted.
Inspection hours are SUM_TOTAL_ON_SITE_HOURS attributed to the inspection start date, without supervisor/trainee hours. Missing hours are omitted; a started inspection may still be open.
Portfolio totals use current mine membership, including events before the current owner or operator's tenure.